18164 - SBSMP - Rev 0
Attached to the e-mail Operation Works Application - OPW19/0266 - 215 David Low Way, Peregian Beach - (EMAIL 2/3) - Site Based Stormwater Management Plan, Acid Sulphate Soil & Groundwater Management Plan.
18164 - SBSMP/0
Page 6
4 EXISTING DRAINAGE PATTERNS
4.1 Existing Infrastructure
Data obtained from the detailed site survey and Dial Before You Dig (DBYD) plans indicate the
following existing drainage infrastructure:
1. A 375mm diameter stormwater main traversing the carriageways of David Low Way and
Sandpiper Court, with a headwall outlet into the nature reserve, south of the subject site;
2. An easement abutting the northern and western boundary of the existing shopping centre
complex within the site, containing a stormwater main ranging from 300mm to 450mm in
diameter, with a headwall outlet into the nature reserve, south of the subject site;
3. A series of stormwater pipes and gully pits directing runoff from the shopping centre
complex to a detention tank and a bio-retention basin prior to discharge to the nature
reserve, south of the subject site;
Refer to Figure 4.1 for the existing stormwater infrastructure and drainage patterns.
N
Proposed
Development
Area
Legend
Sheet Flow Path
Stormwater Pipe
Stormwater Manhole
Stormwater Gully Pit
Headwall Outlet
Figure 4.1 – Existing Drainage Paths & Infrastructure
Site Based Stormwater Management Plan
Reconfiguration of a Lot and Mixed Use Development at 215 David Low Way, Peregian Beach
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.