Delegated Report - Code - Planning OPW24 0125 · OPW24/0125
e. have no construction material, equipment or personnel entering the area/zone except
to undertake approved rehabilitation activities.
*(Refer to Advisory Note)
Fauna Management
20. A qualified person* must be engaged to manage fauna prior and during clearing to:
a. ensure works are carried out in accordance with the approved Fauna Management
Plan, J001259, version 1, dated 01/02/2024; and the Nature Conservation Act 1992.
b. undertake pre-clearing inspections including fauna relocation and removal or blocking
of all vacant hollows.
c. ensure clearing works avoids nesting times of animals and birds.
d. provide a written report to Council with the request for the prestart meeting of all pre-
clearing activities and initiatives.
e. co-ordinate staging and sequence of clearing with fauna protection.
f. protect and recover fauna during clearing operations (fauna not previously removed).
g. manage the translocation of animals and recovery procedures in accordance with
relevant legislation.
h. undertake protection works for mulching of any stockpiled vegetation.
*(Refer to Advisory Note)
Removal of Existing Trees and Vegetation
22. Removal of existing trees and vegetation must be undertaken by a qualified person* and
must include:
a. stump grinding to below finished surface level.
b. rectification to the finished surface levels and materials.
c. no damage to other vegetation for retention.
d. legal disposal of all removed vegetation and debris.
*(Refer to Advisory Note)
24. Vegetation removal, felling and lopping must:
a. retain old growth tree hollows and suitably relocate and distribute for nesting fauna.
b. mulch all other wood and leaf material (without root balls, soil or debris and minimising
weed seeds) for re-usable mulch.
c. have mulch for re-use in landscape or rehabilitation stockpiled and aged for a minimum
of three months.
d. have mulch stockpiles no larger than 1000m3, 2.5m in height and with 10m separation
between piles.
e. allow for existing endemic ground flora to be translocated to suitable landscaping and
rehabilitation areas.
f. conclude with the area being stabilised against erosion, landscaped, rehabilitated and
revegetated.
*(Refer to Advisory Note)
Engineering
Page 11 of 19
Document Set ID: 23410526
Version: 6, Version Date: 14/01/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning OPW24 0125.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.