256. The Developer shall provide Electricity, a TV antennae system and Telecom services to the
resort. All electricity and Telecom services shall be provided underground.
257. All electricity and Telecom services are to be contained with the existing road reserve, external
to the Site. The Developer is to provide street lighting on-site.
Traffic – External
Traffic Management Plan
258. The Developer shall submit a Traffic Management Plan prepared by a Registered Professional
Engineer of Queensland specialising in traffic management for approval by the Manager –
Land Development with the lodgement of any application for operational works for the Site.
259. The Traffic Management Plan shall include, but not be limited to, the following:
259.1.construction vehicle management;
259.2.the number of construction vehicle movements per day on Viewland Drive to ensure
impacts on residents are limited;
259.3.car park provisions during construction.
259.4.limited access management during construction hours;
259.5.signage management;
259.6.operational vehicle management; and
259.7.speed limit requirements.
Traffic Management for Morwong Drive and Viewland Drive
260. Access to the Resort is to be via Viewland Drive from 7:00 am to 7:30 pm and from Morwong
Drive from 7:00 pm to 7:30 am.
261. Appropriate signage to the reasonable satisfaction of the Manager – Land Development and
Manager Land Use advising guests, visitors, employees and invitees of the Resort of the
access arrangements is to be erected. A sign shall be provided at the Morwong Drive cul-de
sac head.
262. Guests of the Resort are to be informed at the time of making a reservation of the access
arrangements on Site.
263. Emergency services, local taxi companies and bus and tour operators are to be informed of
the access arrangements on Site.
264. The Developer is to provide sufficient information at the Morwong Drive entrance to the Resort
and at the Viewland Drive entrance to the Resort to enable a person seeking to enter the
Resort to locate the alternative access if the access initially chosen by the person is closed.
265. The Developer must construct, to the reasonable satisfaction of the Manager – Land Use, a
control mechanism and sufficient turning movements on Site to ensure the split time access
regime is enforced. Such control mechanism will include control barriers that cannot be
operated by guests or visitors of the Resort to gain access to the Resort outside of the hours
specified in these conditions. A gate shall be installed at the northern end of the resort access
road (Alma Way) on Lot 888 where it joins with Morwong Drive but south of the Halse Lodge
entry and shall be accessible at all times to the residents of the ‘Viridian Residences’ on Lot 13
on SP151409; or alternatively the gate shall be installed in a location to the reasonable
satisfaction of the Manager Land Development.
266. Vehicles must not be driven on Alma Way after 7:00pm or parked on Alma Way at any time
south of the southern most gate, ie between that gate and the Viewland Drive exit.
Page 42 of 59
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval - 010.2006.00000823.003 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 329 KB (small file)
- File type
No other editions are linked here.