220711 Noosa Oyster Project - CEMP

Attached to the e-mail Noosa Oyster Project _ Construction and Environmental Management Plan (CEMP).

of 50

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (13.4 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

       3.2.4. Flora and Fauna

                                                                                   Timing /
          Control Measure                                Responsibility
                                                                                   Frequency
          Potential Impact: Damage to trees and root systems
          At the commencement of works sea grass
          will be marked out with star pickets or
                                                                                   Ongoing during
          alternatively a “Chanel” will be marked        Site Supervisor
                                                                                   project
          where it is suitable to transit with minimal
          disturbance to the sea grass
          Excavation near trees to be kept will be
                                                                                   Ongoing during
          avoided and stockpiles kept clear of any       Site Supervisor
                                                                                   project
          tree.
          Potential Impact: Disturbance to endangered species
          Where an endangered species is identified,
                                                                                   Ongoing during
          works will stop immediately and the            Site Supervisor
                                                                                   project
          relevant authority notified.
          Protective fencing will be installed around
                                                                                   Ongoing during
          trees and areas where endangered species       Site Supervisor
                                                                                   project
          are found.
          Any fauna species encountered on site will
                                                                                   Ongoing during
          be relocated by a qualified wildlife carer     Site Supervisor
                                                                                   project
          from an organisation such as WIRES.
          Potential Impact: Spread of weeds
          Weeds will be removed from the site and                                  Ongoing during
                                                      Site Supervisor
          composted or disposed of to prevent spread.                              project




M&J Marine Services                            Page 14                     Environmental Management Plan
Log in to download the original file

220711 Noosa Oyster Project - CEMP.pdf · 13.4 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.