220711 Noosa Oyster Project - CEMP

Attached to the e-mail Noosa Oyster Project _ Construction and Environmental Management Plan (CEMP).

of 50

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (13.4 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

       3.2.5. Community Relations

                                                                                    Timing /
          Control Measure                                 Responsibility
                                                                                    Frequency
          Potential Impact: Public amenity
          Community consultation and information
                                                                                    Ongoing during
          events are being co ordinated by the            Project Manager
                                                                                    project
          principle.

       3.2.6. Traffic

                                                                                    Timing /
          Control Measure                                 Responsibility
                                                                                    Frequency
          Potential Impact: Parking and access to site
          Nominated parking areas will be allocated                                 Ongoing during
                                                          Project Manager
          on site.                                                                  project
          Residents and property owners will be
                                                                                    Ongoing during
          notified about the possibility of an increase   Project Manager
                                                                                    project
          in traffic.

       3.2.7. Waste Management

                                                                                    Timing /
          Control Measure                                 Responsibility
                                                                                    Frequency
          Potential Impact: Unacceptable disposal of site waste
          All material waste will be recorded in the                                Ongoing during
                                                          Site Supervisor
          Waste Register.                                                           project
          All waste removed from site will be
          disposed of in accordance with the                                        Ongoing during
                                                          Site Supervisor
          Protection of the Environment Operations                                  project
          Act 1997 (POEO ACT 1997).
          Appropriate space will be provided for the
          temporary storage of garbage, recyclable                                  Ongoing during
                                                     Site Supervisor
          and compostable waste to ensure separation                                project
          of waste products.
          During works, on-going checks will be
          carried out to ensure correct separation and                              Ongoing during
                                                          Site Supervisor
          re-use of recyclable materials is being                                   project
          maintained.


M&J Marine Services                            Page 15                      Environmental Management Plan
Log in to download the original file

220711 Noosa Oyster Project - CEMP.pdf · 13.4 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.