220711 Noosa Oyster Project - CEMP

Attached to the e-mail Noosa Oyster Project _ Construction and Environmental Management Plan (CEMP).

of 50

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (13.4 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

       3.2.10. Hazardous Materials

                                                                                     Timing /
          Control Measure                                  Responsibility
                                                                                     Frequency
          Potential Impact: Spills and uses of hazardous materials
          All hazardous and/or intractable wastes are
                                                                                     Ongoing during
          to be disposed of in accordance with             Site Supervisor
                                                                                     project
          relevant Authority and EPA requirements.
          All hazardous waste removed from site will
          be disposed of in accordance with the                                      Ongoing during
                                                     Site Supervisor
          Protection of the Environment Operations                                   project
          Act 1997 (POEO ACT 1997).
          Safety Data Sheet (SDS) of hazardous                                       Ongoing during
                                                           Site Supervisor
          substance will be referred to if spills occur.                             project
          All hazardous substances will be recorded
          in the Hazardous Substances Register and                                   Ongoing during
                                                     Site Supervisor
          the SDS recorded in the Safety Data Sheets                                 project
          (SDS) Register.

       3.2.11. Soil Contamination

                                                                                     Timing /
          Control Measure                                  Responsibility
                                                                                     Frequency
          Potential Impact: Spillage and leaking of hazardous material into the soil
          Regular maintenance will be undertaken on
          all machinery and transport vehicles to                                    Ongoing during
                                                    Site Supervisor
          ensure there are no fuel or oil spills or                                  project
          leaks.
          Only trained workers will handle hazardous                                 Ongoing during
                                                     Site Supervisor
          materials.                                                                 project
          All materials will be labelled and stored in                               Ongoing during
                                                           Site Supervisor
          a lock-up with an impervious floor.                                        project
          Safety Data Sheets (SDS) for all hazardous                                 Ongoing during
                                                           Site Supervisor
          materials will be kept on site.                                            project
          All site workers will be trained in spill                                  Ongoing during
                                                           Site Supervisor
          management.                                                                project




M&J Marine Services                             Page 17                      Environmental Management Plan
Log in to download the original file

220711 Noosa Oyster Project - CEMP.pdf · 13.4 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.