220711 Noosa Oyster Project - CEMP

Attached to the e-mail Noosa Oyster Project _ Construction and Environmental Management Plan (CEMP).

of 50

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (13.4 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

2.          Environmental Management Structure and
            Responsibilities
     2.1.   Director/ manager
              • Ensure this EMP is developed and reviewed with adequate consultation; and
              • Authorising approval and amendments to this EMP.
              • promoting and maintaining good environmental management.
              • Implementing this EMP, including education regarding critical changes to the controls or
                safeguards are communicated to supervisors, employees and relevant contractors;
              • Monitoring compliance with this EMP;
              • Investigating reported non-compliances with this EMP.
     2.2.   On site Supervisor/ Person in charge
               • Inducting all workers and sub contractors and directing all site activities in accordance
                 with this EMP
               • To ensure they and their team members comply with this EMP;
               • To ensure adequate and appropriate instructions regarding this EMP are provided to new
                 staff, other contractors as well as any relevant third parties
               • To report non-compliances with this EMP to Management;
               • To complete any required documentation associated with this EMP.
     2.3.   Employees and Sub Contractors
               • To comply with this EMP;
               • To follow instructions from the supervisor or person in charge regarding this EMP;
               • To report all potential environmental impacts/ hazards to your supervisor as soon as
                 possible



                                             Project Manager
                                             Jay      Maartensz




                                            Site Supervisor
                                      John Matelone / Jay Maartensz



     Employees /                                                                                   Sub Contractors
      workers               Table 2.1 Project Environmental Roles & Responsibilities
                            Matrix




M&J Marine Services                                  Page 6                            Environmental Management Plan
Log in to download the original file

220711 Noosa Oyster Project - CEMP.pdf · 13.4 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.