Annex 13 - Schedule 3 - Prescribed Tidal Works
Attached to the e-mail DA Application - Noosa Oyster Project (2 of 3).
Coastal Protection and Management Regulation 2017
Schedule 3. Code for Assessable Development that is prescribed tidal works
Part 3 Performance outcomes and acceptable outcomes
(ii) can be structurally supported by an existing revetment or
seawall or another existing structure;
(b) if a relevant planning scheme standard is more stringent
than the standard mentioned in paragraph (a)—the relevant
planning scheme standard, to the extent it is more stringent than
the standard mentioned in paragraph (a).
12.3 Prescribed tidal works are designed and The design and construction of the prescribed tidal works is Complies with Performance Outcome 12.3.
constructed in a way to ensure they do not consistent with the following standards—
adversely affect the stability of the bed and (a) subject to paragraph (b), prescribed tidal works do not The purpose of the works is not to provide erosion
banks of tidal water. cause, by changing the flow of water, the removal of, or protection, but to restore rock oyster ecosystems
disturbance to, the sediment on the bed and banks of tidal water; throughout the Noosa River.
(b) if a relevant planning scheme standard is more stringent However, Concept Layouts 2 & 3 (segmented
than the standard mentioned in paragraph (a)—the relevant longshore modules most suitable for locations which
planning scheme standard, to the extent it is more stringent than are vulnerable to erosion and adopted for Phase 1) are
the standard mentioned in paragraph (a). anticipated to act as a segmented reef patches and
provide some sheltering to the shoreline from wave
action and vessel wake and result in reduced erosion.
The layout is aligned with the river flows and provide
gaps between reef patches to limit potential for
impacts on natural processes.
The proposed works are not expected to adversely
affect the stability of the bed or banks of tidal waters.
Some settlement or localised scour on the seaward
side may occur and the works are expected to be
reprofiled or topped up in response.
12.4 Prescribed tidal works are designed and The design and construction of the prescribed tidal works is Complies with Performance Outcome 12.3.
constructed using materials suitable for consistent with the following standards—
marine environments, having regard to their (a) subject to paragraph (b), each Australian Standard relevant The rock utilised is to be suitable for use in the marine
ability to resist the following— to the materials that should be used, or the measures that environment. It is not vulnerable to attack by marine
(a) attack by marine organisms; should be taken to treat materials used, for structures, to the organisms, corrosion, deterioration, abrasion,
extent the requirements stated in the Standard apply to immersion in seawater or wave action within the life of
(b) corrosion; structures located in a marine environment; the works. For specifications, refer ICM drawing
NROR-2021-02 Note 2.1.
(b) if a relevant planning scheme standard is more stringent
than the standard mentioned in paragraph (a)—the relevant
12