Annex 13 - Schedule 3 - Prescribed Tidal Works
Attached to the e-mail DA Application - Noosa Oyster Project (2 of 3).
Coastal Protection and Management Regulation 2017
Schedule 3. Code for Assessable Development that is prescribed tidal works
Part 3 Performance outcomes and acceptable outcomes
Signage
6.1 A sign erected or otherwise placed in A sign erected or otherwise placed in position for prescribed tidal Complies with Performance Outcome 6.1
position for prescribed tidal works, other than works, other than a sign erected or placed for safety reasons or
a sign erected or placed for safety reasons or under an Act, is consistent with the following standards— Signage and aids to navigation are to be installed as
under an Act— (a) subject to paragraph (c), a sign erected or placed in position required by MSQ permit conditions. Section 7 of the
(a) is compatible with the character and for identifying prescribed tidal works, or the owner of the works, Project Restoration Plan outlines navigation aid type,
amenity of the works’ immediate surroundings is the only sign erected or placed in position for identifying the signage specifications and signage certification. This
and the locality within which the works are works or owner; selection has been informed by pre-lodgement
located; and discussions with MSQ.
(b) subject to paragraph (c), a sign erected or otherwise placed
(b) is not a dominant feature of the works, in position for prescribed tidal works is integrated into the design a) The aids to navigation are to be of a type
unless the dominance is for safety reasons. and construction of the works; consistent with standard MSQ buoys and are
therefore compatible with the character and
(c) if a relevant planning scheme standard is more stringent
amenity of the works’ locality. SCG has
than the standard mentioned in paragraph (a) or (b)—the
certified that the signage is consistent with
relevant planning scheme standard, to the extent it is more
the requirements of the Coastal Protection
stringent than the standard mentioned in paragraph (a) or (b);
and Management Act.
(d) any other relevant planning scheme standard that is not
inconsistent with the standards mentioned in paragraphs (a), (b) b) The dominance of the signage will be based
and (c). on navigational safety requirements.
Earthwork, vegetation & rehabilitation
7.1 Excavation and filling for prescribed tidal The earthwork and filling for the prescribed tidal works is Not applicable.
works— consistent with each relevant planning scheme standard.
(a) is carried out only to the extent reasonably The works do not include removal of any material,
necessary for the works; and excavation or filling.
(b) does not have a significant adverse effect
on—
(i) the natural features, including the banks, of
the tidal water in the works’ immediate
surroundings; or
(ii) the level of the surface of the land under
the tidal water in the works’ immediate
surroundings or any foreshore near the works.
5