Attachment B - Code Compliance Assessment
Performance Outcomes Acceptable Outcomes Planning Comment
Effects of works
Drainage
PO1 AO1 Complies
Finished surface levels ensure land is free Filled or excavated areas have a minimum To fit within the building height limit, the
draining. gradient of 0.5% and drain to Council’s ground floor is raised to allow sufficient
stormwater infrastructure where available, height for the lower floor level. Compacted
or where stormwater infrastructure is not fill is used to raise driveway and
available, toward the street. landscaping levels to meet the higher
ground floor from the street. There will be
sufficient fall to Rene Street and available
stormwater infrastructure nearby. The
lower ground level is excavated and there
is sufficient fall to available stormwater
infrastructure to the rear.
Hydraulics
PO2 Complies
Change to the levels on site do not have an No acceptable outcome provided There is sufficient stormwater
adverse impact on the flooding and infrastructure capacity in the surrounding
drainage characteristics off-site. area. This development does not interfere
with the characteristics of the drainage line
to the rear of the site.
Geotechnical considerations
PO3 AO3.1 Complies
Earthworks do not result in geotechnical Filling works are undertaken in accordance All earthworks are to be undertaken in
instability on-site or to nearby premises. with Council’s Planning Scheme Policy PSP6 accordance with Council’s Planning
Engineering design standards - roads, Scheme Policy 6 with further details
drainage and earthworks. provided at Building Works stage.
jrey.au | (07) 3106 3221 | [email protected]
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Attachment B - Code Compliance Assessment.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.