Attachment B - Code Compliance Assessment
Performance Outcomes Acceptable Outcomes Planning Comment
At most, there is a cut of approximately 2.9
metres proposed as calculated from the
West Elevation plans.
Infrastructure protection
PO10 Complies
Earthworks and vehicular access do not No acceptable outcome provided As part of the development works, it is not
adversely impact on the capacity, expected that earthworks and vehicular
operations and maintenance of existing access do not adversely impact on the
infrastructure. capacity, operations and maintenance of
existing infrastructure. Works along the
proposed driveway ramp from the ground
floor level to the lower floor level will take
into consideration the location of existing
stormwater infrastructure. Care will be
taken to avoid impact.
Environmental protection Complies
PO11 No acceptable outcome provided The site does not involve impacts to known
Earthworks minimise any adverse impact groundwater, watercourses, drainage lines,
upon groundwater, watercourses, wetlands and native vegetation. Whilst the
drainage lines, wetlands, and native site is adjacent to a biodiversity corridor,
vegetation. earthworks associated with this
development will not impact and erosion
and sediment control measures will be in
place during construction.
Dams
PO12 AO12.1 N/A
Where the site is in the Rural zone— No dam proposed.
jrey.au | (07) 3106 3221 | [email protected]
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Attachment B - Code Compliance Assessment.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.