Council archive · source document
SUPERSEDED - Decision Notice - DBW21 0208 [As Published] · DBW21/0208
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Infrastructure Charges
1. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
Building and Construction Industry (Portable Long Service Leave) Levy
2. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.
Co-ordination of Operational Works Assessment
3. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will result
if all works are lodged in a single application.
Qualified Person
4. For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability
for the development, a qualified person is considered to be a person who:
a. is a Registered Professional Engineer of Queensland (RPEQ); and
b. has a degree in civil engineering or engineering geology; and
c. has a minimum of 5 years’ experience in the field of geotechnical engineering or
engineering geology.
Turtle Habitat Protection
5. To minimise the impact of development on turtle nesting sites and the sea-finding behaviour
of hatchlings, the following actions are recommended to be undertaken during construction of
the development:
a. Construction works are to be restricted to daylight hours during the turtle nesting and
hatching season (October – May).
b. Flood lighting must not be used from October – May (turtle nesting and hatching
season).
6. All lighting should be positioned and managed to reduce sky glow and light spill onto the
beach to minimise disruption to turtle nesting and sea-finding behaviour of hatchlings.
Management measures include reduced intensity, long wavelength lights; shielded, low to
the ground, and directed onto areas of interest; low reflectance building surfaces and paint;
and tinted external glass. The following should be incorporated into the development:
a. All windows, glass doors, glass panels and sky lights facing the beach (NE, E, SE) to
have 15% visible light transmittance tinting.
b. All windows, glass doors, glass panels and sky lights facing the beach (NE, E, SE) to be
fitted with opaque blinds, to be drawn from 8:00 pm during turtle nesting and hatching
season (October – May).
c. Indoor and outdoor paint/surfaces/fixtures to be matte and dark in colour and have a
maximum reflectance value of 30%.
Page 5 of 8
Document Set ID: 22407726
Version: 3, Version Date: 04/05/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.