2018-08-07 S&O Agenda - Att 1 to Item 1 - Draft Bridges Asset Management Plan

of 33

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
4.5    Bridge Maintenance Plan
Maintenance is fundamental for the ongoing management of the bridges. It is considered an
investment rather than a liability. The bridges rely on maintenance costs as these are a significant
annual investment that directly influence the potential for a bridge asset to reach its intended useful
life. The ongoing development of asset knowledge through asset inspections, improved maintenance
inspections and activities, subsequent defect monitoring and repairs are fundamental in developing
sustainable intervention levels for renewal and replacement of bridge assets.


                 Actual       Actual          Actual       Budget       Budget        Forecast     Forecast
 Year            2014/15      2015/16         2016/17      2017/18      2018/19       2019/20      2020/21
 Maintenance     $2,051,375   $2,297,024      $2,091,252   $1,839,426   $1,680,328    $1,935,120   $1,757,895
                 Forecast     Forecast        Forecast     Forecast     Forecast      Forecast     Forecast
 Year            2021/22      2022/23         2023/24      2024/25      2025/26       2026/27      2027/28
 Maintenance     1,778,787    1,637,718       $1,464,387   $1,418,155   $1,541,528    $1,541,528   $1,721,079


Figure 3: Annual Maintenance Costs by Asset Group

Ongoing maintenance costs are identified to ensure council understands the whole of life costs
associated with the day-to-day management of bridges. The figure below identifies the long term
financial commitment required in maintaining assets. In order to maintain assets to an acceptable
level, the cumulative costs over a ten-year period will equate to $23m. It is proposed to develop a
more detailed list of maintenance activities per annum, by bridge assets, through the utilisation of
the T1 asset management system. Annex C highlights the budget for 2018/19 Maintenance.
However, more detail and longer term planning for maintenance has been identified as an
improvement from this AMP.


                10 Year Operating and Maintenance Expenditures Forecast
 $25,000,000




 $20,000,000




 $15,000,000




 $10,000,000




  $5,000,000




         $-
               2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29

                       Maintenance         Operating       O&M Totals      Cumulative Total


Figure 4: Bridge Operating & Maintenance Costs & Forecast



Asset Management Plan: Road Bridges                                                                Page 12
Log in to download the original file

2018-08-07 S&O Agenda - Att 1 to Item 1 - Draft Bridges Asset Management Plan(PDF, 2MB).pdf · 2.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.