ORDINARY MEETING AGENDA 15 JANUARY 2015
Landscaping
9. The development site must be landscaped. The works must be undertaken in
accordance with The Noosa Plan, Planning Scheme Policy PSP03
Landscaping Plants and Guidelines and the approved plans.
10. Dense screening vegetation must be provided for the full length of the black
PVC chainlink fence and the bin enclosure along the Rene Street frontage.
11. All landscape works must be established and maintained in accordance with
the approved design for the life of the development, and in a manner that
ensures healthy, sustained and vigorous plant growth. All plant material must
be allowed to grow to full form and be refurbished when its life expectancy is
reached.
12. All landscape works must be maintained generally in accordance with the
approved design for the life of the development.
Site Access and Driveways
13. A sealed access driveway must be provided from the common property road to
all parking and manoeuvring areas of the development. The works must include
in particular a driveway crossover in accordance with IPWEAQ standard
drawing SEQ R- 051 or R-052
Car Parking
14. A minimum of 17 car parking spaces must be provided and marked on the site.
The car parking must be made available and accessible at all times while the
use is open for business. The works must include in particular:
a. carspaces 1-5 and 12-15 must be allocated as staff parking spaces
b. 1 disabled parking space within the total
c. crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities
d. wheel stops for carspaces 7-12 to prevent vehicles entering the biobasin.
The wheel stops must be designed and installed in accordance with
AS/NZS2890.1:2004.
15. All car parking areas and access driveways must be maintained exclusively for
vehicle parking and manoeuvring and kept in a tidy and safe condition at all
times.
16. Directional signage must be provided to direct visitors and customers to the car
parking spaces provided on site.
Service Vehicles
17. Service vehicle parking, manoeuvring and standing spaces must be provided
on the site.
Stormwater Drainage & Quality
18. The site must be provided with a stormwater drainage system connecting to a
lawful point of discharge.
19. Any overflow from rainwater tanks installed on site must receive treatment
within the bioretention basin prior to release from the site.
Earthworks and Retaining Walls
20. All fill and associated batters must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to
Council. All earthworks must be undertaken in accordance with the provisions
Page 9 of 32
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.