2020-07-07 P&E Agenda - Item 3 - Attachment 1 - TNC Project Management Plan

of 89

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
 Annual/Final progress reports (2020,2021,2022)        TNC                      Not Started
 Six monthly report cards (2020,2021,2022)             TNC                      Submitted


A1.3 Establishment of a Project Technical Advisory Group (TAG) for shellfish ecosystems restoration and associated
activities:

Timeline: 3 months from appointment of Project Manager

    •     Terms of reference drafted, including meeting timeframes, rolling agenda items, roles and responsibilities
    •     Committee members nominated as representatives
    •     Committee members invited/confirmed as representatives
    •     Regular meetings chaired by TNC Project Manager


A1.4 Participation and delivery of public education and engagement forums (9) and media statements (3)

Timeline: Three forums within first 12 months. Additional 6 forums in years 2 and 3.

    •     Forums and key audiences identified, feedback forms/surveys developed
    •     Key messages, presentations and external documents (i.e. project brochures) developed
    •     Forums delivered
    •     Media statements drafted by TNC, approved by NSC
    •     Media statements jointly released, media monitoring engaged

A1.5 Annual and six-monthly project reporting

Reports must include details on progress made against deliverables, monitoring and evaluation and financial
expenditure (income/expenditure).

Timeline: Ongoing over 3 years

    •     Reporting templates, developed and agreed (template attached as Annex 3)
    •     Draft reports sent to NSC (and where appropriate, Technical Advisory Group) four weeks prior to final
          completion date
    •     Final report revised and completed

Reporting Milestones

Table 3. Reporting dates and milestones over the three year project period.

 Report Type                             Draft Due                              Final Due
                                            st
 Year 1 Annual Report 2020               31 July 2020                           31st August 2020
 Six Monthly Status Report 2021          31st December 2021                     31st January 2021
 Year 2 Annual Report 2021               31st July 2021                         31st August 2021
 Six monthly Status Report 2022          31st December 2021                     31st January 2022
 Final Report 2023                       31st July 2022                         31st August 2022




                                                                                                                     22
        BRING BACK THE FISH: PROJECT MANAGEMENT PLAN
Log in to download the original file

2020-07-07 P&E Agenda - Item 3 - Attachment 1 - TNC Project Management Plan(PDF, 3MB).pdf · 3.5 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗