Negotiated Decision Notice - 010.2007.00000256.001 [As Published] · 132007.256

of 20

Text shows just the words. Original shows the document exactly as it was published.

                                                                                        2007/256



Roof Water & Stormwater Drainage
44.   Roof runoff from any new building shall be directed to a rainwater storage system or tank that
      is installed to ensure water from the tank is used for external uses (such as watering gardens,
      irrigation, ornamental ponds, water features, outdoor cleaning, etc) and for use in flushing of
      toilets internal to the building.   All rainwater tanks are to be designed and installed in
      accordance with the Queensland Development Code (QDC), Part 25 – Rainwater Tanks, and
      shall be part of the plumbing application in conjunction with the building approval. The
      location and capacity of the tanks shall be in accordance with the approved Surface Water
      Management Plan (SWMP) and be clearly shown on the plans submitted for Operational
      Works approval and any overflow shall be directed as required by the SWMP.
45.   All stormwater drainage (including roof water overflow from the rainwater storage system)
      shall be collected and discharged so there is no net increase in stormwater runoff from the site
      for up to and including a Q100 rain event.
46.   Stormwater drainage permitted to drain from the site shall be discharged to Council’s existing
      drainage structures in Gateway Drive. If required, the applicant shall upgrade the existing
      drainage system. Plans of the drainage design shall be prepared by a Registered
      Professional Civil Engineer and submitted to Council prior to obtaining a Development Permit
      for Operational Works. A Development Permit for Building Works shall not be granted until a
      Development Permit for Operational Works has been issued in regard to the drainage
      scheme.
47.   As the site is proposed to be filled, appropriate stormwater drainage pipes shall be installed or
      overland flowpaths created within the site to collect and discharge stormwater runoff from all
      adjoining properties to prevent additional ponding/flooding on these properties.
48.   All site stormwater drainage shall be by means of a gravity system.
49.   All stormwater drainage lines including inter-allotment drainage shall be inspected by closed
      circuit television (CCTV) prior to commencement of the approved Use.
      CCTV inspection will be carried out by Council's CCTV contractor and arranged by Council
      following satisfactory completion of construction works. The developer will be responsible for
      the full cost of CCTV inspection, including any additional inspection necessary following defect
      identification and rectification. This charge is payable prior to the issue of Operational Works
      approval and will be determined on the unit rate basis current at the time of approval.

Surface Water Management
50.   To ensure that polluted run-off does not enter Council’s stormwater drainage system or the
      downstream ecosystem, stormwater run-off from the carparking areas and the driveways shall
      be treated and maintained in accordance with an approved Surface Water Management Plan.
      The Cardno Surface Water Management Plan dated 8 February 2008 shall be amended to
      reflect the conditions of this approval and the modified layout approved herein.
      The design, construction and maintenance of treatment measures shall be in accordance with
      the Healthy Waterways Water Sensitive Urban Design Technical Design Guidelines for South
      East Queensland (2006 or more recent edition).
      The amended Surface Water Management Plan shall include a requirement for monitoring to
      be undertaken for a period of three years after the commencement of the use. Monitoring
      results shall be submitted to Council on a quarterly basis for their records in digital form.

      Monitoring results presented to Council shall include:

           qualitative statements detailing the presence/absence of scour, sediment and litter
             build-up within bioretention basins and inlet and surcharge pits; and
           results of water quality monitoring undertaken during rain events up to a Q3 month
             event that create a suitable amount of runoff to allow for the collection of water
                                                                                          7 of 20

Used in these records

About this file

File size
101 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice - 010.2007.00000256.001 [As Published].pdf · 101 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.