                                                                                         2006/138

      Sewer Mains
35.   The site shall be connected to Council’s existing sewerage reticulation systems and be
      constructed in accordance with Council’s standards and requirements at no cost to Council.
36.   The existing sewer main that traverses the rear of the site and the ‘zone of influence’ (taken as
      the area within a 45-degree angle measured from the invert of the sewer main to the finished
      surface level) shall be accurately located and determined by a licensed Surveyor and shown
      on all plans submitted for Operational Works approval.
      To ensure Council’s sewer main is accessible for maintenance purposes and is protected from
      risk of damage no structures requiring a building permit (eg. swimming pools, dividing walls
      exceeding 1m in height, etc) shall be constructed within this ‘zone of influence’ and as such
      the applicant shall ensure the Operational Works plans and Building plans are in compliance
      with this requirement (in particular the location of the swimming pool may need to be revised).
37.   A registered easement shall be created over the zone of influence of all sewers within the
      subject site and over those parts of the subject site that are impacted upon by sewers on any
      adjoining sites. The easements shall generally be parallel to and centred over the sewer main
      and be equivalent in width to twice the depth to invert level of the sewer at the deepest point
      within the allotment (measured from the finished surface) and not less than 3.0m wide. In this
      regard a licensed surveyor shall accurately locate all sewer mains and determine the
      necessary width of the easement, which shall be shown on all plans submitted for Operational
      Works / Building Works approval. To this extent the surveyor shall certify that the sewer and
      the zone of influence is wholly contained within the easement to be created.
      In addition to this the Applicant’s Solicitor shall give Council’s Solicitor an appropriate
      undertaking in writing that the Title Deed and the easement documents will be lodged at the
      Land Titles Office and any additional Titles Office forms or requisitions requiring the consent of
      Council will be attended to promptly.
      A duly executed copy of the easement shall be submitted to Council for perusal prior to the
      use commencing.
      Any changes required by Council’s Solicitor must be corrected immediately.
      Town Water Supply
38.   The site shall be connected to Council’s existing town water supply and be constructed in
      accordance with Council’s standards and requirements at no cost to Council.
39.   Each water connection to the water reticulation system shall extend to the property boundary
      and be metered. Each individual unit shall be provided with its own water meter. All fees for
      the supply of water meters shall be paid to the Council.
      Headworks Contributions
40.   Deleted
      Earthworks and Site Stability
41.   Any filling works required on site shall be carried out in accordance with Section 3.8 of
      Council’s Engineering Design Standards Manual and so as not to cause the additional
      ponding of water on any adjoining lands. Details and depth of filling works must be provided
      with the application for a Development Permit for Operational Works.
42.   Earthworks carried out on site shall not affect the structural integrity of any of the existing
      fences or structures that border the development site. Fences that are affected shall be
      replaced prior to the Building Certifier issuing the Certificate of Classification. In this regard
      any fences to be replaced shall be clearly shown on the plans submitted for Operational
      Works approval.


                                                                                      Page 5 of 17

Used in these records

About this file

File size
188 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Letter - Change to an Existing Approval - 010.2006.00000138.002 [As Published].pdf · 188 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.