ATTUNGA HEIGHTS PRELIMINARY EMP

2.1.9 Air Quality Management Plan

Issues

Objectives

2.1.9.1
Maintain air quality levels to within
the EPA’s targets values. Inctuding,

but not limited to, levels of dust and
smoke levels (particles) and pollutant
from machine exhausts. Refer
Appendix E

Management Procedures

Particular Responsibilities

Corrective Action

The nature of the on-site sandy soils and the vegetated nature of the site will assist in mitigating against dust and the prohibition of
buming will avoid smoke related issues. Nevertheless, construction will involve earthworks, vehicle movements and other activities
with the potential to produce air-bome particulates locally.

To control dust and smoke in accordance with the requirements of the Environmental Protection Act, 1994 and the Environmental
Protection (Air) Policy 1997 which preclude the release of dust in a manner that is unreasonable and causes environmental harm
(Part 4, Division 14, Environmental Protection (Air) Policy 1997)

Implementation Strategy Performance Indicators

Vehicles and machinery will be serviced regularly and tumed off when not required, rather than left idling, | Absence of air quality related

Bare earth will be kept watered, especially on windy days. complaints from adjacent neighbors
Disturbed areas shall be of minimum size to allow an area to be worked and re-established and stabilised or others.

prior to moving off the site.

 

Service and maintain machinery and vehicles, avoid long periods of idling. Avoid long continuous fire-prone windrows of cleared
vegetation. Water, road works, batters and ail bare earth when dry and especially when being worked and in windy conditions.
Establish a complaints procedure and advise neighbors.

On-site staff wilt receive induction in dust suppression reduction techniques.

Contractor — Establish a complaints recording procedure and notify neighbours, control trucking and other sub-contractors;
Meet performance indicators for air quality as defined in the EMP. Implement and maintain the Air Quality Management Plan.

Works identified as causing undue dust will cease immediately and the Contractor will investigate the problem and implement
appropriate mitigation measures.

Management procedures may need to be modified to achieve compliance (to the satisfaction of the Superintendent and
Environmental Auditor). Review air quality measures and modify accordingly.

Preliminary EMP: Attunga Heights issue: 1

 

Chenoweth EPLA

Revision: 0 12/12/2007

Used in these records

About this file

File size
14.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_2555 - Operational Works - Drainage Stormwater Vegetation [As Published].pdf · 14.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.