° Problems, remedial actions undertaken and the outcomes of those actions;
° Incidents, accidents and complaints.

The Superintendent shall supply Council’s Environmental Officer with copies of any environmental
monitoring data, reports, documents etc within 48 hours of written request.

Environmental Audit Reports shall be submitted to Council within seven (7) days of finalisation by the
Environmental Auditor.

1.6.3 Access & Inspections - Construction

The following persons will be permitted to inspect any part of the site or works at any time in the
company of the Superintendent (or representative):

¢ Council’s nominated Environmental Officer (or representative); and

e Environmental Auditor.

1.7 DESIGN AND CONSTRUCTION PLANNING

Extensive environmental investigation and planning for the Attunga Heights development has been
undertaken to ensure compliance with the development conditions. These previous studies have informed
this EMP. Other information used in preparation of this EMP includes:
e Site-specific investigations;
e Experience in EMP performance; and
e Preliminary construction and sequencing plans for the Attunga Heights project (see Construction
and Sequencing Plan prepared by Qantec McWilliam Pty Ltd.).

1.8 TRAINING AND AWARENESS

Prior to commencing work on site all project staff and subcontractors shall undertake a site-specific
environmental induction. The induction includes the following:

¢ Environmental values of the site in context of adjacent and nearby sensitive areas;

e Environmental risks associated with construction and access;

¢ Compliance with relevant statutory obligations including but not limited to “Environmental Duty
of Care” and “Duty to Report”;

¢ Identification of environmental documentation and content of the EMP including requirements for
compliance with;

e Level of environmental commitment expected; and

e Environmental reporting requirements for environmental matters and incidents (potential and
actual).

Where training is identified for specific EMP elements, and/or for environmental issues, contro] measures
and equipment, the Superintendent shall arrange training for relevant staff contractors.

 

Preliminary EMP: Attunga Heights Issue: 1 ‘|i4
Chenoweth EPLA Revision: 0 12/12/2007 |

 

 

 

Used in these records

About this file

File size
14.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_2555 - Operational Works - Drainage Stormwater Vegetation [As Published].pdf · 14.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.