Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
4. Environmental Assessment
Proposed Controls
Risk
Risk
HOC
Aspect Risk Responsible Person
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Environmental Harm HIGH 5 Erosion and Sediment Control Plan (ESCP) to be designed by suitably qualified person. M Site Management
☑ Natural form sediment in Installation and maintenance of ESCP devices as per plan to be implemented and monitored as per
waterways, waterways instruction from suitably qualified person.
stormwater, or
overland flow Complete regular inspections on sediment and erosion plan and in consultation with the plan owner to
adjust the sediment and erosion controls as the site changes
Failure to implement HIGH 3 Implementation of required controls on site with monitoring of implementation completed through the M Site Management
adequate controls Weekly Inspection or as required in the engineer notes.
Sediment tracked off HIGH 5 • Vehicles to be inspected prior to leaving site for excessive soil/mud on tyres. M Site Management
site Contract Partner’s
• Sediment traps to be installed on stormwater inlets. Stockpiles need to be managed to ensure run
off does not leave site and enter stormwater and stockpiles need to be located away from land
overflow paths
Sediment tracked off HIGH 4 All road/ kerb and channel environmental devices to be maintained and cleaned during construction. If M Site Management
site required street sweeper to clean roads of sediment from travel paths of trucks and vehicles Contract Partner
Contamination of EXTREME 4 Separate washout areas for: M Site Management
waterways by • Paint Project Management
incorrect site washout
facilities • Plaster
• Concrete
• General
Contamination of EXTREME 1 Washout for paint and plaster are not to be connected to sewer or disposed of in stormwater. L Site Management
waterways by Paint and plaster wash out to be maintained to ensure effective containment.
incorrect site washout
facilities
Protected flora and HIGH 5 Prior to commencement of works all protection zones to be identified and established as per the DA M Site Management
☑ Work in fauna adversely requirements. Where required monitoring of flora / fauna is to occur, and records maintained.
environmentally impacted Any observed native animals or pest on site are to be managed by a licenced animal catcher
sensitive areas
Pollution of HIGH 5 Where practical, waste to be segregated into recycling materials and bins clearly mark to identify each M Site Management
☑ Waste surrounding areas bin type. Project Management
Management Plan
Waste tracking certificates for traceable waste to be completed by licence contractors
Project Hazard/Risk Assessment / Page 17 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 836 KB (small file)
- File type
No other editions are linked here.