Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
Proposed Controls
Risk
Risk
HOC
Aspect Risk Responsible Person
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Nuisance dust HIGH 3 Work areas and trafficable areas are to be dampened down for dust suppression. L Site Management
☑ Dust controls
Water to be used with plant and equipment generating dust Contract Partner
Nuisance dust HIGH 3 Vacuums to be used with equipment in alignment with relevant safe work method statements L Site Management
Contract Partner’s
Nuisance dust HIGH 5 Limit dust generating activities during high winds where possible L Site Management
Contract Partner
Non-compliance with HIGH 5 • Site operations between 7:00am and 6:30pm Monday to Saturday (or as per DA/BA requirements) L Site Management
☑ Noise DA conditions
management • Where out of hours works are required application and approval from local council to be obtained.
• Noise Management Plan implemented as required.
• Site planning and positioning of noisy plant and equipment to be considered prior to
commencement on site (including but not limited to crane selection).
• Planning of the works with potential to create excessive noise/vibration.
• Reduced hours for rock breaking activities to reduce impact to neighbours.
• Place machinery away from noise sensitive areas where possible
Environmental harm N/A 5 Implementation of Acid Sulphate Management Plan with required controls. N/A Project Management
☒ Acid Sulphate Soils from run off or Site Management
Per initial
incorrect disposal of
Geotech
spoil
Damage to property HIGH 5 Vibration management process to be implemented in areas with a high risk of damage to surrounding M Site Management
☑ Works near other during earthworks buildings. Vibration monitoring devices to be installed where possible issues are identified. Contract Partner
buildings or historical
buildings Damage to property EXTREME 3 • Screening installed in accordance with demolition/staging plans. M Site Management
during demolition Contract Partner
• Initial hand demolition to assist in some areas where stages are too close to each other for machine
demolition.
Introduction of fire EXTREME 5 Project is not located in a Fire Ant Zone L Site Management
☒ Fire ant zone ants into new areas Imported fill to be from within local area HSE Advisor with
Implementation of Fire Ant Environmental Work Method statement and required controls. BSBWHS414 OHS Cert
4 / Manager
Failure to identify fire N/A 5 1 x member of the Site Management Team to complete Fire Ant Awareness Training and display the N/A Site Management
ants and respond certificate in the site office
Project Hazard/Risk Assessment / Page 18 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 836 KB (small file)
- File type
No other editions are linked here.