Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118

of 80

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                                                                                Proposed Controls                                                                          Responsible
Activity           Hazards




                                        Risk
                                                                                                                                                                                                Risk




                                                 HOC




                                       Initial
                                       Rating
                                                                                   (1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)                                           Person



                                                                                                                                                                                              Residual
           Exposure to live          EXTREME     5     A copy of certification of the disconnection of services from the relevant authority is retained on site.                                               Site
           services (gas,                                                                                                                                                                                 Management
           electrical, sewerage,                                                                                                                                                                           Demolition
           refrigerant gases etc.)                                                                                                                                                                       Contract Partner

           Flying particles /        EXTREME     3     Controls will be in place to prevent falling objects hitting the public in adjoining areas by:                                                          Site
           materials / falling                                                                                                                                                                            Management
                                                       - Closing adjoining areas (to exclude all persons) to the extent necessary to prevent objects contacting persons.                                   Demolition
           objects
                                                       - Erecting perimeter containment screening along each part of the structure from which an object could fall.                                      Contract Partner
                                                       - Another control measure to stop objects from falling on or hitting persons
           Flying particles /        EXTREME     4     Where overhead protective structures are provided over public walkways (between a public place and the building being                                   Site
           materials / falling                         demolished) the structures shall consist of a horizontal platform of solid construction with vertical supports and the                             Management
           objects                                     platform shall:                                                                                                                                     Demolition
                                                                                                                                                                                                         Contract Partner
                                                       - Extend from the common boundary to the edge of the carriageway for the full length of the boundary,
                                                       - Have a clear height above the footpath of not less than 2.1m,
                                                       - Terminate at the edge of the carriageway with a continuous solid up stand projecting not less than 0.5m above the
                                                           platform surface and
                                                       - Together with its supports, be designed for a uniformly distributed live load of not less than 7kPa.
           Flying particles /        EXTREME     5     Where the demolition is adjacent to another building controls will be implemented to protect:                                                           Site
           materials / falling                                                                                                                                                                            Management
                                                       - the other building; and                                                                                                                           Demolition
           objects
                                                       - any person entering/leaving the other building; and                                                                                             Contract Partner
                                                       - any person who is on top of the other building (as applicable).
           Flying particles /        EXTREME     4     Where perimeter containment screening is erected or altered controls will be implemented to prevent any part of the                                     Site
           materials / falling                         screening falling on a person.                                                                                                                     Management
           objects                                                                                                                                                                                         Demolition
                                                                                                                                                                                                         Contract Partner
           Flying particles /        EXTREME     3     Where demolished materials are to be lowered onto / into a public place, the area will be properly barricaded to prevent                                Site
           materials / falling                         members of the public entering.                                                                                                                    Management
           objects                                                                                                                                                                                         Demolition
                                                                                                                                                                                                         Contract Partner
           Flying particles /        EXTREME     4     Where scaffolding is provided it shall comply with AS 1576 Scaffolding (SET) and shall-                                                                 Site
           materials / falling                                                                                                                                                                            Management
                                                       - be erected before the demolition work starts on the side of the building that is being demolished where it faces a public                         Demolition
           objects                                         place and may be kept erected until the work is finished; and                                                                                 Contract Partner
                                                       - be certified by an engineer; and
                                                       - be rated as heavy duty; and



                                                                                                                                            Project Hazard/Risk Assessment / Page 70 of 160

Used in these records

About this file

File size
836 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdf · 836 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.