Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118

of 80

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                                                                                   Proposed Controls                                                                             Responsible
   Activity        Hazards




                                    Risk
                                                                                                                                                                                                        Risk




                                             HOC




                                   Initial
                                   Rating
                                                                                      (1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)                                              Person


                                                                                                                                                                                                      Residual
                                                   With a competent person defined as –
                                                   a person who has acquired, through training, qualifications or experience knowledge and skills, including:
                                                   • sound knowledge of relevant Australian Standards, relevant codes of practice and other relevant legislation,
                                                   • ability to read and interpret drawings
                                                   • sound knowledge of, and competence in, the risk management process for the erecting, altering and dismantling of formwork including:
                                                               - hazard identification and risk assessment - measures to control exposure to risks - safe work practices and procedures - how to
                                                               plan and prepare formwork.

Planning for   Activity          EXTREME     5     All tasks involving formwork will have an approved SWMS in place. The SWMS will address all high-risk activities including work at heights                        Site
formwork       planning and                        for tasks that are undertaken where a worker could fall 2m or more and scaffold stripping activities along with formwork hazards and                          Management
installation   hazard                              controls.                                                                                                                                                      Formwork
               identification                                                                                                                                                                                      Contract
                                                                                                                                                                                                                   Partner
               Falling objects   EXTREME     3     Where works to erect or dismantle formwork are undertaken, the adjoining area will be closed to the public or perimeter containment                               Site
                                                   screening will be erected.                                                                                                                                    Management
                                                   Where works to erect or dismantle formwork are undertaken, the area on site will be excluded to non-essential workers not involved in the
                                                   task.

               Access and        EXTREME     3     QLD –                                                                                                                                                            Site
               egress                                                                                                                                                                                            Management
                                                   Stair tread access and egress is to be used as the primary source of access to a formwork deck unless it is not reasonably practicable to do
               Slips trips.                        so.
               Emergency                           Access requirements as per Formwork code of practice 2016 are to be applied:
               retrieval




               Access and        EXTREME     4     NSW - Access to the live working deck will be through one of the following methods.                                                                              Site
               egress                                                                                                                                                                                            Management
                                                   -   Extension Ladder – Tied top and bottom, at an angle of 4:1 and protrude at least 1 metre above the landing height.
               Slips trips.                        -   Hoist
               Emergency                           -   Internal stairs
               retrieval
                                                   -   Portable stairs
                                                   -   Mobile scaffold stairs
                                                   -   Perimeter scaffold stairs.


                                                                                                                                                   Project Hazard/Risk Assessment / Page 111 of 160

Used in these records

About this file

File size
836 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdf · 836 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.