Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
Proposed Controls
Activity Risk Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Contact with sharp HIGH 2 Where possible, cranked starter bars will be purchased. Site Management
objects
Contract Partner
Trips and falls HIGH 5 Safe access will be provided to the working area with working platforms at the appropriate level and enough space for Site Management
equipment and barricades.
Contract Partner
Impacts of heat HIGH 5 Work groups are to manage the risk of heat by implementing the heat management process of their employer. Site Management
Contract Partner
17.3 Precast Panels
Planning for the Inadequate EXTREME 5 Pre-Cast / Tilt Panel Installation Checklist on Procore will be actioned prior to the lifting of precast panels. Site Management
installation planning in advance
of the activity All parties below will sign off on the confirmation of completion of all items. Contract Partner
Site Manager / Formwork Supervisor / Panel Crew Supervisor / Intermediate Rigger / HSE Advisor
Activity planning EXTREME 5 SWMS / Safety plan to be approved for the activity prior to the commencement of the work outlining: Site Management
and hazard
identification Methods of controlling vehicle access around the pre-cast work area Contract Partner
Any hazards associated with overhead power lines, trenches, and recent excavations.
Crane size and placement requirements
Erection sequence with panel weights and bracing layout
Orientation and identification of panels
Inadequate EXTREME 5 The following documentation must be obtained and attached to the pre-cast panel checklist: Site Management
planning in advance
of the activity Panel birth certificates noting the panel is at confirmed lifting strength in accordance with engineer requirements. Formwork Supervisor
Engineer supplied panel drawings – includes lifting plan. Panel Crew Supervisor
Propping Plan – Engineer supplied drawing. Intermediate Rigger
Where spandrel panels are used a formwork handover / engineer sign off - formwork engineer to sign off
Where dead men anchor points are used – deaden drawings, and engineer sign off is required as per COP.
Project Hazard/Risk Assessment / Page 119 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗