Council archive · source document
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
Proposed Controls
Activity Risk Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Concrete test reports for supporting concrete structures i.e. slab top and bottom, dead men – supplied by concrete
supplier
Insufficient crane/ EXTREME 3 Crane lifting capacity is not to exceed 85% without approval from Project Manager and Team HSE Manager Site Management
lifting equipment
considerations Contract Partner
Training and EXTREME 5 The panel erection crew must be holders of intermediate rigging (RI) licence or be trainees. Site Management
instruction
Trainees engaged in formal training under RTO must be supervised and logbooks showing previous training must be Contract Partner
kept.
Installation of panels Collapse of pre-cast EXTREME 4 A minimum of two braces will be secured to each panel unless specified by the engineer and indicated on the erection Site Management
concrete units drawings. Where only one brace is used there will be a minimum of two fixings at each end.
Contract Partner
Collapse of pre-cast EXTREME 1 No part of the bracing support system will be removed until the panel has been permanently anchored and inspected Site Management
concrete units by the Pre-cast installer refer – Precast Installation Checklist
Contract Partner
Plant colliding with EXTREME 4 Where plant is required to be operated near panels and bracing the following controls or a combination of controls Site Management
bracing shall be in place:
Contract Partner
Bump stops.
Para webbing / bunting
Water barriers/physical
Signage
Plant colliding with EXTREME 2 Where plant is required to be operated near panels the use of a scissor lift will be used where possible to reduce the Site Management
bracing risk of contact with the panels or bracing
Contract Partner
People interaction EXTREME 3 An exclusion zone will be established so that only those persons directly involved with the erection of panels are in Site Management
in installation area the area while lifting is taking place. The exclusion zone will be set up so that it includes an area where persons cannot
resulting in injury be struck either by: Contract Partner
The crane falling over,
The panel being lifted falling over (approx. 1.5 x height of largest panel), or
Project Hazard/Risk Assessment / Page 120 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 836 KB (small file)
- File type
No other editions are linked here.