27. The existing formation in Val Crescent must be upgraded from the existing
formation in Goodchap Street and extending to the tangent point in the kerb line
adjacent to the northern boundary of No 3 Val Crescent. The works must be
undertaken in accordance with an Operational Works approval and must include
but not be limited to:
works designed and constructed in accordance with Council’s Planning
Scheme Policy PSP 5 – Engineering Design Standards – Roads, Drainage
and Earthworks (section 3.19(d) – Industrial/Commercial – Local road);
the full width of the formation in Val Crescent;
reinstatement of existing linemarking.
This Condition is imposed pursuant to s145 of the Planning Act 2016 being non-
trunk infrastructure.
Bus Stop relocation
28. The bus stop and associated infrastructure must be relocated in accordance with
Translink’s requirements. These works must also include the installation of a new
shelter in accordance with Council’s standard drawings. In this regard please
note that Council has a contract with a 3rd party to manufacture and install bus
shelters. The developer must:
carryout adjustment works to the kerb line and/or road linemarking along
the new bus stop bay as necessary to achieve compliance with the
applicable standards for cycle lanes requirements. The works must be
included as part of the Operational Works application.
liaise with the bus shelter manufacturer/installer and create all necessary
conditions for their works (i.e. concrete slab, etc.);
advise Council of timing for the installation of the bus shelter and report as
soon as possible any changes to the programme.
This condition is imposed pursuant to s145 of the Planning Act 2016 being non-
trunk infrastructure. The relocation of the bus stop is only to facilitate the
development and therefore no offset of the Infrastructure Charges is applicable.
29. Written approval from Translink’s Temporary Closures Team must be provided
as part of the Operational Works application, confirming that the application for
impact to the public transport bus network has been accepted and complies with
DTMR’s “Industry Guideline: A guide to managing public transport impacts”.
Site Access and Driveways
30. Sealed access driveways must be provided from Goodchap Street and Val
Crescent to all parking and manoeuvring areas of the development. The works
must be undertaken in accordance with an Operational Works approval and must
include in particular:
driveway crossovers generally in accordance with Council’s standard
drawing RS-051
suitable safety measures, including warning signage, to improve driver
awareness of pedestrians and enhance pedestrian safety. Warning
signage must be provided near the exit driveways to warn motorists of
pedestrian movement along the frontage street
Page 16 of 42
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.