                                                                                    REC14/0005

      Easements
13.   A drainage easement must be created within proposed Lot 103. The easement must be:
      (a) Of sufficient width (approximately 4.5m) to encompass all elements of the
            combined underground pipe and open drain solution (underground pipe (Q10
            flows), batters, bunds, etc. and a 1.5m maintenance track),
      (b) In favour of Lot 26 SP151406 to connect to a legal point of discharge as defined in
            QUDM.
      (c) Alignment of the underground pipe, open drain, and easement is to be determined
            through operational works application (as per condition 9(b) above).

14.   A drainage easement must be created within proposed Lot 101. The easement must be:
      (a) In favour of Lot 26 SP151406 and proposed Lot 103,
      (b) Centrally located over the existing piped drainage system connecting proposed Lot
            103 and Lot 26 SP151406 to the existing stormwater discharge point in Gateway
            Drive.

15.   Unless otherwise agreed in writing by the relevant service provider, any public or third
      party infrastructure located on the subject site must be placed within an easement
      registered against the title of the property.

16.   All easements must be designed in accordance with the planning scheme and granted
      at no cost to the Grantee. Where the Grantee is Council or a service authority, the
      easement documentation must be in accordance with the Grantee’s standard easement
      terms. Draft easement documentation must be submitted to Council for endorsement.

17.   All works must be kept clear of any existing or proposed easements on the subject land,
      unless agreed otherwise in writing by the Grantee.

      Earthworks and Retaining Walls
18.   All fill and associated batters must be undertaken in accordance with an Operational
      Works approval, and contained entirely within the subject site unless written permission
      from the respective landowner(s) is provided to Council.

19.   All retaining walls must be designed and constructed in accordance with the planning
      scheme and must be certified by an RPEQ where exceeding 1.0m in height. All
      retaining walls that are publicly accessible and exceed 1.0m in height must be fitted with
      a commercial grade safety fence.

      Damage to Services and Assets
20.   Any damage caused to existing services and assets as a result of the development
      works must be repaired at no cost to the asset owner at the following times:
      (a) where the damage would cause a hazard to pedestrian or vehicle safety,
           immediately; or
      (b) where otherwise, upon completion of the works associated with the development.
      Any repair work which proposes to alter the alignment or level of existing services and
      assets must first be referred to the relevant service authority for approval.




                                                                                 Page 4 of 10
Log in to download the original file

Attachment C- REC14.0005 Negotiated Decision Notice.pdf · 113 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.