Construction Management Plan

3.4    Services and finishes
Prior to slabs being placed in the buildings the services are to be installed in ground as per the approved
design. These works will commence within the building but will not be completed until the fitout of
appliances is complete.

After the structure is complete, the services will commence to be installed. These works will commence within
the building but will not be completed till the façade to that level is complete. The façade provides edge
protection for the men working near the edge and provides weatherproofing for equipment that is water
sensitive. The works will be organised in several passes, with what we term “rough in of services” being the
first pass which is all services that can be installed before the façade is completed. Finishes are normally
commenced in earnest when the façade is installed to that floor. The services will be scheduled to be
completed enough to allow finishes to commence in our programming. Plant, equipment and materials will
be lifted to the floors via several means depending on what stage the building is at.

3.5     External works
The completion of external wall cladding will allow the external works to be commenced and completed in a
timely manner. The works will also include making good any areas that have been affected by the construction
of the project. Once these areas are rectified, casting of external hardstands, footpaths and crossovers will
commence. Landscaping works will commence concurrently in order to stabilise the ground and place soil in
garden beds prior to closing area with new cast concrete slabs.

All environmental controls installed as part of the earthworks, will be monitored and maintained during the
construction of the warehouses. On commencement of external works according the operation works
approvals, existing services like street lights, fire hydrants and the like, will be protected as required during
the construction of the approved works.


3.6 Construction sequence and planning
The locations and types of plant may vary depending on the results of more detailed planning as the design
solidifies and the availability of plant is firmed up. There will be 3 distinct phases requiring different material
handling logic, to construct the building efficiently and minimise impact on surrounding streets and
neighbours.

The phases are:
Phase 1. Site establishment; bulk excavation, detailed excavation and footings installation
Phase 2. Structure
Phase 3. Finishes and external works

Each phase will not happen in isolation. Phase 2 and 3 will happen simultaneously once the structure is
sufficiently complete, to allow the finishes trades to commence on lower levels.




Authorised Managing Director                UNCONTROLLED WHEN PRINTED                                     Page 9 of 14
Commencement Date: 27 August 2020                IMS-4-T3 Version 3                         Review Date: 27 August 2022
Log in to download the original file

Construction Management Plan V2.pdf · 1.3 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.