Construction Management Plan
3.0 Construction Methodology
3.1    Demolition and excavation
The bulk earthworks phase will consist of removal of the existing vegetation into a stockpile for processing
onsite and then removed in chip form from site. The topsoil and organic matter will be stripped into stockpiles
for removal during the works. The civil design has been completed to utilise fill material from the site to
minimise the import and export of fill from the site. This will limit the truck movements required to undertake
the works for this project.

Existing services within the site will be located and either capped if redundant or modified if they are to be
used as temporary services for the works according to the approved design. If this is unachievable than all
services will be held temporarily and pumped out or supplied as required. The retaining wall systems will
commence during the bulk earthworks phase and completed to allow the final level to be completed. The
overall Design drawings and specifications can be provided as a standalone document (if required) and is not
included in this CMP.


3.2    Substructure works
From the Geotechnical report we envisage that the substructure works will be a combination of Strip and high
level pad footing arrangements and some minor bored piers. As the detailed excavation is complete,
foundations will be cast, in ground services installed, and the ground will be prepared for the structure and
the slabs will be cast on ground.
3.3 Structure

The structure trades and works will be supported by mobile cranes for lifting of materials, propriety perimeter
edge protection will be used to provide fall protection. Where required perimeter scaffolding will be installed
within our property to allow the external cladding trades to complete their works including painting etc.
Loading and unloading of these materials and equipment will be completed outside of peak traffic times and
the working hours stipulated in the Development Approval.




Authorised Managing Director               UNCONTROLLED WHEN PRINTED                                   Page 8 of 14
Commencement Date: 27 August 2020               IMS-4-T3 Version 3                       Review Date: 27 August 2022
Log in to download the original file

Construction Management Plan V2.pdf · 1.3 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.