2.0 Construction Management
2.1 Approach
The major external constraints on the project are:
• Maintaining smooth traffic and pedestrians flow with minimal disruptions to the surrounding streets
• Undertaking works with minimal impact on neighbours
• Ensuring existing roads maintain in clean state, all erosion and sediment controls in place to protect
existing council storm water system
• Main access and parking on viewland Drive. Entry and exit must be set up taking into account existing
road visibility in order to avoid potential collisions or danger to pedestrians.
o Traffic control will be used as needed to assist the flow of external traffic
• Upon commencement, our project team’s immediate tasks will be to:
o Locate a project office, site accommodation and facilities
o Undertake a survey of the site and complete a dilapidation report of surrounding properties
and assets
o Confirm the locations of existing services and obtain all necessary permits and licences and
approvals
o Arrange for the installation of temporary services – power, water and sewer to service the site
works and the amenities.
2.2 Approvals
The works will be completed in one go without any staging of the works and this will be reflected in the Building
Approval and Development Application. A development approval is available for the works, which includes
clearing and bulk excavation works. Operational works pre-start meeting with Noosa Council is required, prior
to commencement of the building works on site. Development approval contains conditions that certain
reports will need to be completed, submitted and approved before works can commence. Some of these
reports needing approval are:
• Construction management plan (CMP)
• Erosion and sediment control (completed by separate contractor as part of the bulk earthworks)
Prior to commencing temporary modification or arrangements, further approvals may be required from Noosa
Council including but not limited to:
• Application / Notification to Work on Council Property
• Temporary Footpath Closure Application
• Crossover application
It is proposed that a single Building Approvals (BA) will be obtained from a qualified private certifying authority
(PCA) prior to commencement on site. It is proposed that the BA will be approved in the following sequence:
• Structural and foundation works
• Base Build Certification
• Services and Internal Fit Out
The staging of the BA’s will allow works to commence, whilst affording time for those works requiring intense
design time such as structural and finishes works. The net effect is an overall reduction in total development
construction time.
Authorised Managing Director UNCONTROLLED WHEN PRINTED Page 6 of 14
Commencement Date: 27 August 2020 IMS-4-T3 Version 3 Review Date: 27 August 2022