NOOSA COUNCIL IDAS Development Application Decision Notice 10 of 17
39. Vegetation within the southern covenant area (5m wide) is to be reinstated with broadleaf “Sir Walter”
buffalo turf; or preferably reinstated with low native and endemic plants and mulch to provide a fully
planted ground cover in compliance with any requirements of the fire management plan. The covenant
area shall be fully stabilised within 2 weeks of the completion of earthworks in this area.
Lot 4
40. Existing trees on the site located within the western covenant area (3 meters wide) are to be retained and
protected from construction damage, except where required to be removed due to the requirements of the
approved ecological restoration plan.
41. The boundary of the covenant area is to be fenced along the eastern, northern and southern boundary
with star picket and wire as temporary fencing prior to any construction work commencing on the site, and
maintained for the duration of the construction process. No access into this area is permitted except for
ecological restoration purposes.
42. The Lot 5 - OS2 and OS4 open space boundary perimeter (where it meets road reserve and lot
boundaries) is to be fenced with star picket and 2 strand wire as temporary fencing prior to any
construction work commencing on the site, and maintained for the duration of the construction process.
Appropriate signage shall be erected on the fence in accordance with management plan requirements.
No access into this area is permitted except for ecological restoration purposes. No removal of natural
vegetation is to occur in the Lot 5 - OS2 and OS4 open space areas for the creation of fire breaks or fire
buffers.
Lot 5 - OS7
43. The applicant shall comply with the requirements of the approved Site Rehabilitation Plan for any
undeveloped land area of the lot located within OS7 and beyond the road reserve. No works are to occur
within OS7 except ecological rehabilitation works.
General
44. The management of acid sulfate soils on the site shall comply with the requirements of the Construction
EMP and the Acid Sulfate Soil Investigation by Golder Associates, with existing acidity within the soil to be
managed.
45. Stormwater and sediment control management on the site shall comply with the management plan
requirements regarding the protection of wallum froglet habitat at all times.
46. All relevant work specified in the site rehabilitation plan, ecological restoration plan and open space
management plan shall be completed to the reasonable satisfaction of the Manager Land Use prior to
Council endorsing the Plan of Survey.
47. Additional reinforcement plantings shall occur in private open space and protected areas (OS3, OS6,
OS7, Lot 4 covenant area) as ecologically required to reinstate the natural vegetation. Additional
reinforcement plantings shall also occur in the Lot 5 public open space area OS2 & OS4 as ecologically
required to reinstate the natural vegetation prior to dedication to Council. All work shall be in accordance
with the requirements of the Site Rehabilitation Plan.
48. No unrestrained dogs shall be permitted on site during construction.
49. The provision of high-speed telecommunications infrastructure is required to be provided to all lots.
Provision for full broad band capacity to each lot is to be provided that gives access to broadband
infrastructure capable of providing data transmission at technologically advanced speeds existing at the
time of development. Such capability is to be provided either by underground conduit or other low visual
impact method. The intra-site broadband infrastructure shall connect to a suitable external broadband
network.
Vegetation Removal
50. Clearing of existing vegetation on the site shall only occur where removal is required to enable
construction of roads, stormwater drainage, water & sewer reticulation, accesses or pegging of surveyed
boundaries, or sequential clearing of lots to allow approved earthworks to occur.
Suitably qualified cultural monitors and wildlife spotters and handlers shall be available on site during the
works to assess any cultural findings and manage any wildlife disturbed.
NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@a000e63d\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2007.00001242.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 58 KB (small file)
- File type
No other editions are linked here.