and clearly shown on plans submitted for operational works.
d. Any relocation/reinstatement of existing services in the road verge.
These works are to be undertaken at no cost to Council.
Site Access and Driveways
19. A sealed access driveway must be provided from Wimmers Lane to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance
with an Operational Works approval and must include in particular:
a. a driveway crossover generally in accordance with RS-051 and any associated
addendum.
Car Parking
20. A minimum of 23 car parking spaces and 2 motor cycle spaces must be provided and
marked on the site for the commercial development, and made available and
accessible at all times while the use is open for business. The works must be
undertaken in accordance with an Operational Works approval and must include in
particular:
a. pedestrian routes in accordance with the conditions of this Decision Notice .
b. 1 disabled parking space within the total.
c. dimensions, crossfalls and gradients in accordance with Australian Standard
AS2890: Parking Facilities.
21. All car parking areas and access driveways must be maintained exclusively for vehicle
parking and manoeuvring and kept in a tidy and safe condition at all times.
Pedestrian and Bicycle Facilities
22. Pedestrian and bicycle facilities must be provided for the development. The works
must be undertaken in accordance with an Operational Works approval and must
include in particular:
a. a 2 metre wide footpath along one side of Wimmers Lane and Emerald Street.
b. the resealing of the existing asphalt path fronting the development.
23. Pedestrian and bicycle facilities must be provided for the development and include:
a. 10 bicycle parking spaces and 5 lockers; and
b. one shower cubicle with ancillary change room.
Stormwater Drainage
24. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval and the Queensland Urban Drainage Manual, and must include in
particular:
a. works generally in accordance with the Stormwater Layout Plan. Fig 1.2 Revision
B prepared by Callaghan & Toth dated 6 July 2022;
b. extension of the site stormwater system to accommodate stormwater from the
existing external drainage pipe from Lot 2 on RP44101 to the east; and
c. the use of gravity stormwater drainage and not surcharge pits.
This condition is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Page 7 of 63
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.