Asset Management Plan
Noosa Aquatic Centre
Technical Levels of service
Performance Level of Service Measure Measurement Target
Measure Criteria
Reliability The ability of the Mean Time Corrective Work Greater than 95%
NAC to consistently between failure Orders reliability
perform its intended (MTBF)
function on demand
and without
degradation or
failure.
Maintainability The probability that Mean Time to Labour hours in Less than 10 hours
a given Repair (MTTR) planned and
to respond to any
maintenance action, corrective work
high priority
for an item under orders
reactive work.
given conditions of
use can be carried
out within a stated
time interval
Quality The NAC Facility Asset condition Number of 1 – That defects are
Assets are rating asset condition prioritised and
maintained within rectified for assets
the 1-3 asset to be maintained at
condition criteria. a minimum
standard of
condition 3.
Page 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.