Appendix D- Engineering Assessment
Earthworks Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: Sept 2020
Performance Outcomes Acceptable Outcomes Solution1 Comments Council Use
& residential development.
Local amenity AO4.1 RO4.1
PO4 The following measures are implemented Water trucks shall be used to
Undertaking earthworks does not – minimise dust emissions. An
adversely impact on the amenity of the (a) regular water spraying of exposed Erosion and Sedimentation Control
local area by way of dust, noise or visual areas to suppress dust; Plan shall be prepared (prior to
amenity. (b) provision of dust stabilised or sealed commencement of construction).
internal roads;
(c) protective covering of exposed areas All disturbed areas will be stabilised
that are left for more than 2 weeks; should they be exposed for more
and than 2 weeks.
(d) unless a development permit provides
otherwise, disturbed areas are
revegetated using species identified
in Council's Planning Scheme Policy
PSP2 Landscaping.
AO4.2 RO4.2
Earthworks are undertaken only during the Filling and earthworks will only be
hours of 7:00am to 6:00pm, Monday to undertaken between the hours
Friday and 7:00am to 3:00pm on Saturday. nominated in AO4.2.
No work is undertaken on Sunday or
public holidays.
Vegetative waste AO5.1 RO5.1
PO5 Cleared vegetation is transported off-site Any vegetated waste encountered
Vegetation cleared from a development for disposal in an approved green waste will be dealt with in accordance with
site is disposed of in an environmentally disposal facility. the acceptable outcomes of PO5.
responsible manner. AO5.2 RO5.2
Cleared vegetation is mulched on-site and The proposal complies. Refer to
reused for landscaping of the finished RO5.1.
development.
AO5.3 RO5.3
Cleared vegetation is disposed of for the The proposal complies. Refer to
purpose of firewood RO5.1.
AO5.4 RO5.4
Disposal of vegetative waste by burning off The proposal complies. Refer to
1
Solution: Acceptable Solution Page 2 of 5
A/S Alternative Solution D:\JOBS\23-Jobs\23098 - 5 Pearl Street, Cooroy\Civil\Reports\ESA\Working\Appendices\NSC Earthworks Code 2020.docx
N/A Not applicable to this proposal Job: 23098
Rev: 0
Site Address: 5 Pearl Street, Cooroy 22/09/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.