Part 7 of 37 Appendix 5 - Water and Sewer Infrastructure Report MCU12/0208
Very large file (29.5 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
~,.., Carclno Noosa on Weyba
Water Supply and Sewerage Analysis
6.4.1.1 Alternative Treatment Options
Should the programmed augmentation works not be completed by the expected December 2014 date, a few
sewage disposal options exist including capturing flows onsite or tankering to another treatment plant.
Based on the expected loads to be generated, onsite treatment with effluent reuse for irrigation or discharge
to nearby waterways would not be a possibility. There exists insufficient land of suitable soil profile and area
to be able to utilise effluent reuse in an efficient manner, with stormwater harvesting being of more suitable
beneficial use for open space irrigation. In addition, the limited capacity of the site’s soils to receive effluent
without release to ground or surface waters coupled with the sensitive nature of the receiving nearby waters
(Lake Weyba) including its value as a declared Fish Habitat Area and a habitat for threatened species such
as the Wallumfroglet, would make on-site treatment a last resort option.
In the interim, based on the assumption occupation of the site (and hence flows) will increase gradually over
time, the following is proposed:
> Construction of SPSNW1 and the gravity main discharging to SPSNW1 to be included in the development
subdivision works
>
Discharge of initial flows to SPSNW1 and tankering as required to the Coolum STP.
> As flows and tankering costs increase, a more permanent solution may be required. By this stage, the
discharge to Noosa STP may be an option. If not, then flows could either be treated onsite with a
packaged treatment plant with tankering disposal or a main constructed to discharge to the Coolum STP.
6.4.1.2 Alternative Network Option
Should the capacity of the Noosa STP be limited, the installation of low pressure sewers within the
development would be considered to assist in reducing flows to the Noosa STP. The use of low pressure
sewers within the development would be viable, given the topography and the requirement of pump stations
for a typical gravity sewer network, described in Section 6.3.
The use of low pressure systems can reduce the depth and size of sewerage infrastructure. In addition it is
expected that the total design flow (PWWF)would reduce with the low pressure system. The use of a low
pressure sewerage network can assist in reducing flows, as inflow and infiltration can be significantly
reduced. In this instance the design flow for low pressure sewers can reduced by at least half, refer (Table
4-2),as the design flow is Peak Dry Weather Flow (PDWF)for the system.
Northbrook Corporation Pty. LId Version 3 28 November 2012
5101-19 Commercial in Confidence Page 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 7 of 37 Appendix 5 - Water and Sewer Infrastructure Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 29.5 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.