Council archive · source document
Part 7 of 37 Appendix 5 - Water and Sewer Infrastructure Report MCU12/0208
Very large file (29.5 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
([D)MWH. Noosa on Weyba Water Network Performance Assessment
2 Hydraulic Model
2.1 Model Update
A review of the ’Unitywater Planning Model -
Water’ H20MAP Water model was undertaken for the
Noosa Industrial DMA and the following pipes were updated into the model:
NEW-P001, 150 mm diameter main, 330 m in length, located at Noosa Civic.
NEW-P002, 150 mm diameter main, 100 m in length, located at Noosa Civic near Rene
Street.
NEW-P003, 150 mm diameter main, 420 m in length, located along Rene Street.
The updated pipes are shown below in Figure 2-1.
Water Main
r~’IT’)~’tf->p:g’~
l!}.[Q Q ~:&:.i1t,i ~
Figure 2-1: Updated Model Pipes
2.2 Model Demand
A total water demand for the site of 2,416 EP has been estimated by Card no based on current SCRC
planning information. MWH have confirmed that demand conversion factors used are inline with the
Noosa Planning Scheme Policy and no revision is necessary. The EPs considered for the site are
summarised in Table 2-1.
Status: Draft 22/06/2012
Project number: Page 2 Our ref: Noosa on Weyba WS Assessment.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 7 of 37 Appendix 5 - Water and Sewer Infrastructure Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 29.5 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.