Traffic Management Plan_IMS-04-05_D (001) FOR APPROVAL
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn Traffic Management Plan
▪ Construction Commences October 2020
▪ Construction Completion December 2020
Refer to Appendix 2 for a more detailed copy of the construction program provided by Shadforth.
2.3 Key Personnel and Contact Details
Contact Name Position Company Phone Email
Mark Bain
Mark Bain Client [email protected]
Constructions
0488 383
Doug Reynolds Administrator TOD Consulting [email protected]
370
Out of Hours 0407 395
Darryl Hart Shadforth [email protected]
Contact 496
0417 736
James Harris Project Manager Shadforth [email protected]
105
0407 395
Darryl Hart Site Supervisor Shadforth [email protected]
496
Health and Safety 0400 524
Mark Lonergan Shadforth [email protected]
Manager 763
0450 607
Andrew Hussey Traffic Officer Shadforth [email protected]
330
Table 2.3 Key Personnel and Contact Details
2.4 Stakeholder Details
During all construction phases, the project team will communicate to the Administrator the planned construction
activities and any impacts these activities may pose on the public / community; including changed traffic
conditions or disruption to services. The community and all mode user groups will be informed of changes via
a variety of means: Examples being letter box drops and or Variable Message Sign (VMS) and construction
signage
Key stakeholders include, but are not limited to:
▪ Noosa Council
▪ Local residents and businesses
▪ General public
Engagement with the community will be ongoing throughout the works and consultation with local stakeholders
will be conducted by Shadforth personel.
2.5 Working Hours
The normal hours of onsite work will be:
▪ Monday to Saturday 6:30am - 6:00pm - excluding public holidays
▪ No Work Sundays and Public Holidays
IMS-04-05_D - Reviewed May 2019 Document Uncontrolled When Printed Page 12 of 30