Traffic Management Plan_IMS-04-05_D (001) FOR APPROVAL

of 30

Page text shows just the words. Original shows the document exactly as it was published.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                                                              Traffic Management Plan


All out of hours works will be subject to appropriate approvals from the relevant authorities. The relevant
council is to provide written approval of the submitted this TMP and associated TGS’ prior to Shadforth
mobilising to site.

2.6 Complaints Management

A development information board will be provided at the site entry in a clear and appropriate location. This will
provide the necessary contact details of the onsite manager.

Complaints procedures will be handled as follows:

Complaints directly to the Site Manager - Shadforth will maintain a complaints register that will record all public
complaints made to them directly. The register will record dates, details and actions taken for future reference.
The complainant will be notified by phone or email of the outcome. The Administrator may be notified of any
complaints received and a copy of the register will be made available upon request.

Complaints made to Noosa Council, Shadforth will work with the department to resolve the issues in a timely
manner and appoint expert consultants to assist if necessary. E.g. Civil and Traffic Engineers.

2.7 Asset Management

All road line markings and traffic signs within the vicinity of the site, will not be affected during the construction
phase. There may be a need for temporary removal or modification to existing kerbs and landscaping for
crossovers.

Any changes, damage or deterioration of road pavement, kerbs, traffic signs and line markings that have
occurred as a result of development works will be replaced and reinstated accordingly. Shadforth will ensure that
pre and post records of the affected area will be recorded for future reference. It is noted during the pre-
construction condition assessment of the existing infrastructure shows signs of fatigue and pavement failure /
cracking throughout.




IMS-04-05_D - Reviewed May 2019                  Document Uncontrolled When Printed                        Page 13 of 30
Log in to download the original file

Traffic Management Plan_IMS-04-05_D (001) FOR APPROVAL.pdf · 1.1 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.