ENVIRONMENTAL MANAGEMENT PLAN Cc y Cardno

PROPOSED CHILDCARE CENTRE, SUNSHINE BEACH

1. PREAMBLE TO THE ENVIRONMENTAL MANAGEMENT PLAN

1.1 Terminology

The term Superintendent refers to the present owner/developer of the site, and its
successors in title.

The Contractor refers to the party or company performing construction works on site, and
includes all employees of the Contractor and sub-contractors.

The Consultant refers to the civil engineering design consultant employed by the
Superintendent.

Council refers to the Sunshine Coast Regional Council
EPA refers to the Environmental Protection Agency

EMP refers to the Environmental Management Plan

1.2 Program and Contractual Obligations

The EMP is divided to reflect the two phases of the construction program, construction and
operation.

The construction phase refers to the period from the commencement of works on site to
the substantial completion of the works. The Contractor is generally responsible for
ensuring that the provisions of the Environmental Management Plan are met, except for
certain planning or design issues, which are explicitly noted as being the responsibility of
the Superintendent or Consultant, as appropriate.

The operational phase refers to the period following completion of the construction
activity, whether for an individual element of the works, or the entire project.

Operational phase relates to the period from substantial completion to the expiry of the on-
maintenance period (sometimes referred to as the defects liability period, or the defects
correction period). In these cases, the Contractor is generally responsible to ensure that
the provisions of the EMP are met during this period, and that the permanent works (gross
pollutant traps, rehabilitation works etc.) function as intended.

Upon the expiry of the on-maintenance period, infrastructure works (roads, drainage etc)
will be accepted by Council, who then become responsible for their maintenance. Council
may wish to adopt its own environmental management and monitoring program during the
operational phase.

In these cases, the EMP should be regarded as a condition of the contract between the
Contractor and the Superintendent. Although the Superintendent may hold ultimate
responsibility to ensure that the proposed development complies with relevant
environmental legislation, such as the Environmental Protection Act (EPA) 1994 and the
Environmental Protection (Water) Policy 1997 (EP(W)P), its duties regarding construction
are subordinated to the Contractor by the contract.

 

Comiskey Group 1 18 June 2008
Environmental Management Plan Rev: 1 238401

Used in these records

About this file

File size
11.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

08_1056 - Operational Works - Roadworks, Stormwater & Earthworks [As Published].pdf · 11.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.