ENVIRONMENTAL MANAGEMENT PLAN CC Cardno

PROPOSED CHILDCARE CENTRE, SUNSHINE BEACH

Table C5.1
Erosion and Sediment Control Measures

 

EVENT ACTIVITY

 

Prior to vegetation disturbance | Construction of retardation basins in areas subject to disturbance
or earthworks activity

 

Commencement of Instatlation of silt fences using appropriate geotextile mesh or other
construction material around any areas likely to be disturbed, to capture all eroded
material.

Use of other mechanisms such as soil stabilization techniques, to further
prevent sediment transport from the site.

Construction of low earth bunds around the upstream side of any
working area, so as to divert upstream drainage around the site.

 

During vegetation clearing and | Stacking and removal of nominated vegetation.
earthworks
Stockpiling and stabilization of excavated topsoil and other soil materials
to prevent erosion.

Maintenance of minimum ground-opened area at any one time.

 

After completion of earthworks | Re-vegetation and stabilization of affected areas, using stockpiled
topsoil, so as to prevent erosion and sediment transport.

 

After completion of project Vegetation of overland flow paths and any disturbed areas to eliminate
ongoing erosion.

 

 

 

 

Table C5.2
Schedule of Inspection for Erosion and Sediment Control Measures

 

 

 

Period Frequency | Location Type Parameters to be Monitored

Whilst Weekly All erosion control Visual Check to ensure that erosion control

temporary measures measures are in place and are

sediment functioning satisfactorily.

control

measures Retention ponds Visual e Degradation of water quality

are in place and treatment « Signs of erosion, such as gulley
areas erosion

e Accumulation of sediment at
discharge points

 

Daily during | All erosion control Visual Check for damage, bypassing,

wet weather | measures deposition of excessive silt, scour etc.
including sediment
traps, silt fences,
GPTs etc

 

 

 

 

 

 

 

 

Comiskey Group 13 18 June 2008
Environmental Management Plan Rev: 1 238401

Used in these records

About this file

File size
11.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

08_1056 - Operational Works - Roadworks, Stormwater & Earthworks [As Published].pdf · 11.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.