6 Due to the migration and spawning activities of commercially and recreationally important
species of fish within the area, dredging works must not be undertaken:
during the months of June and July; and
during the two days prior, the days of, and the two days after the new and full moons in the
month of August.
7 Monitoring of the completed Stage 1 works, as defined within the Proposal Details of Condition
1, must be undertaken annually for a reasonable number of years (dependent on the outcome
of the monitoring) by a suitably qualified person and must be concluded with an annual
monitoring report. Each annual monitoring report must be provided to the Manager, Planning
and Assessment, Fisheries Queensland, PO Box 5083 SCMC, Nambour QLD 4560. The
monitoring report must include an evaluation of the completed Stage 1 works; specifically, their
effectiveness in combating ongoing erosion, and an evaluation of the need for further works.
8 A written report which details the completed fisheries development works must be provided
within fifteen (15) days of the completion of the works, to the District Officer, Queensland
Boating and Fisheries Patrol, PO Box 20, Tewantin QLD 4565, and the Manager, Planning and
Assessment, Fisheries Queensland, PO Box 5083 SCMC, Nambour QLD 4560. The report
should contain confirmation of the amount of disturbance to marine plants, confirmation of the
total amount of dredge material, as-constructed drawings and an overview of the construction
methodology and timeframes.
9 OFFSET CONDITION
A Deed, or other formal written agreement, for fish habitat offsets is to be entered into
between The State of Queensland, acting through its agency the Department of Employment,
Economic Development and Innovation (DEEDI), and Sunshine Coast Regional Council. The
impacted marine fish habitat outlined in Condition 1 is to be offset in a manner that is
acceptable to Fisheries Queensland and compliant with the Queensland Government
Environmental Offsets Policy and Fisheries Habitat Management Operational Policy FHMOP
005: Mitigation and Compensation for Works or Activities Causing Marine Fish Habitat Loss.
The offset/s will preferably be documented within an offset package for the Noosa River Spit
Erosion Protection Works and may include: a) direct offsets through inputs for the protection,
creation or enhancement of fish habitats and fisheries resources; or b) indirect offset financial
contribution to be allocated to fish habitat projects for the protection, creation or enhancement
of fish habitats and fisheries resources; or c) a combination of a) and b). The offset Deed, or
other formal written agreement, must be executed by both parties within twelve (12) months of
the issue of the decision notice for this approval.
Basis for inclusion of conditions:
• The Department of Employment, Economic Development and Innovation must assess the
development application against the purposes of the Fisheries Act 1994. This application can
only comply with those purposes, including promoting ecological sustainable development, if
compliance with the abovementioned conditions is achieved.
Delegate of the
Chief Executive
Date..... hlu....
Department of Employment, Economic Development and Innovation Page 3 of 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
DEEDI Approval to request to change and existing development approvalRelated documentApplication case desk ↗
About this file
- File size
- 4.0 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.