column 1 column 2
Including amendments to 8 June 2018
Specific Outcomes Acceptable solutions (if accepted
The Noosa Plan
development subject to requirements)
Probable solutions (if code assessment)
properties
AND
O3 Finished surface levels ensure land is free S3.1 No solution provided
draining.
O4 Filling or excavation does not adversely S4.1 Fill material placed over services does not
affect sewer, stormwater or water utility impose any additional surcharge loading on the
infrastructure. service.
Editor’s note S4.2 Where excavation is carried out-
Council encourages building methods that avoid the c) a minimum cover of 600mm is maintained
use of fill, such as suspended floor construction and around all utility infrastructure (to top,
stepping down slopes rather than cutting and filling.
sides and base of services); or
d) a retaining wall is provided to support the
soil surrounding the service;
AND
S4.3 Compaction with a vibrating roller is not
carried out within 600mm of any utility
infrastructure.
O5 Development does not adversely impact S5.1 Buildings or other structures within the
on the Lake Macdonald water supply. Lake Macdonald catchment (indicated on Figure
14-15) are located above the 98.5m AHD level.
Electricity supply infrastructure
O6 Uses and works maintain an adequate S6.1 Buildings and structures (including
safe distance from electrical infrastructure swimming pools, sheds, tennis courts or
including substations, overhead powerlines, outbuildings) are not constructed under
power poles and transformers. overhead electricity transmission lines, or within
electricity easements.
Steep slopes and Landslide hazard areas
O7 Detached houses and associated uses S7.1 If on premises identified as a Landslide
are sited or constructed to maintain the safety of Hazard Area on Overlay Maps OM1.3–9.3 or on
people and property from the risk of landslide. steep slopes, the use does not—
a) involve the removal of vegetation other
than grass from use areas;
b) involve excavating or filling of more than
50m3 of material (other than placement of
topsoil not exceeding 100mm in depth
relative to natural ground level;
c) involve cut or fill with a vertical depth of
more than 2m relative to natural ground
level;
d) redirect or impede water flows in an
existing watercourse or stormwater drain;
or
e) involve construction of an on-site effluent
disposal system;
OR
S7.2 A site specific geo-technical report
prepared by a registered professional engineer
either—
a) certifies that the site is not at risk from
14-101
Building Works Code
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.