GENERAL COMMITTEE MEETING AGENDA 16 MAY 2022
It is recommended that Council endorse the use of the Disaster Management Reserve
restricted cash to progress this $100,000 work as an out-of-budget funding allocation.
3. Procurement
a. The original engagement of Erscon for emergency works was in accordance with
section 234 of the Local Government Regulation 2012 – ‘A local government may
enter into a contract for goods and services without first inviting written quotes
or tenders if the contract is entered into under an LGA arrangement’.
b. In consultation with the Procurement Branch, Erscon Engineering Pty Ltd
(Erscon) were directly sourced in February 2022 via Local Buy Arrangement BUS
262-0317 Engineering and Environmental Services (LGA arrangement), to
undertake work in leading our counter disaster activity.
c. For the services proposed under this report it is proposed that Erscon be
engaged under LGA arrangement – Local Buy LB279 Project Management
Services (Civil Infrastructure).
d. An Invitation to Quote (ITQ) was issued to Erscon under the above LGA
arrangement on 22 April 2022.
o A subsequent review of the offer from Erscon demonstrates that the
schedule of rates and project methodology that matches the expected
criteria set out in the Tender. This offers Council a high confidence of
quality outcome by way of recovery of reconstruction costs from DRFA.
o A Probity Plan has been approved by Infrastructure Services which outlines
suitable justification along with confirmation of no conflicts of interest.
e. The option to seek multiple/competitive quotations for these services would result
in delay along with a loss of recently learnt information about Council essential
assets that require reconstruction.
f. Additionally, the ability to secure similar services at this point post the flood event
would be at risk due to the demand for services across multiple councils and
Government agencies.
g. Infrastructure Services now seeks to engage Erscon directly to project manage the
reconstruction of essential assets within Noosa Shire Council. Further to this,
Erscon are to advise and where approved, execute construction works that provide
a more resilient asset outcome for Noosa Shire Council. For all projects, Erscon
must ensure funding opportunities using the DRFA are maximised and no works
will be undertaken without a cost recovery plan being approved.
4. Direct Source Justification
a. Value for Money by reducing risk exposure
Erscon has already been contracted to work in these key areas undertaking
some of Counter Disaster activities and Emergency Works actions. If Council
does not engage Erscon, the ability to engage a suitable supplier of
equivalent experience is very low.
A market scan indicates that other notable disaster recovery suppliers have
taken contracts elsewhere or are large infrastructure suppliers focused on
more substantial projects such as single sites totalling $30,000,000.
A delay in engaging a supplier is likely to impact on the completion of the
program of work, compromising the deadlines set by QRA for submission
and then final acquittal. There are over 20 sites requiring treatment over
the next 24 months.
The supplier is continuing to work at the original rates, despite opportunity
Page 11 of 96
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.