GENERAL COMMITTEE MEETING AGENDA 16 MAY 2022
submitted before DRFA
deadline of 30 March 2023.
The sooner Council has the
contract executed, the
sooner application,
approval and
commencement of works
can occur at high-risk sites
such as Black Mountain Rd
landslip.
Contract award is
recommended to occur as
soon as possible in order for
the consultant to not move
onto other clients.
o They have rejected
Sunshine Coast
contract in favour of
Noosa Council
o With rain event
occurring 9 May, prior
client Mt Isa will be
looking to secure
services.
Safety Risks Mitigation
Erscon fail to meet safety standards Erscon are appointed as Principal Contractor responsible
or conduct work safely for workplace health and safety for each site.
Erscon are to submit to Council necessary management
plans, Safe Work Method Statements, Job Hazard
Analysis 9or similar) and other documents as required.
Ongoing surveillance by Council will be undertaken during
the construction period.
Scope & Quality Risk Mitigation
The contractor fails to construct the ERSCON is highly skilled and highly experienced in work
scope of work to the minimum in relation to disaster reconstruction, especially in the area
standard. of road recovery.
The workmanship will be monitored with regular Council
surveillance.
Resource Risk Mitigation
Availability of necessary sub- Erscon have already demonstrated in the prior contract
contractors due to market activity their ability to attract quality sub-contract suppliers.
from affected LGA’s at the same
Noting the scale of this project Council is planning for a
time.
dedicated resource (Disaster Recovery Consultant) to
assist during the outset of this project to provide project
management, procurement support, surveillance and
contract administration support.
Whilst it is possible to utilise Council internal resources,
22/23 and 23/24 already has large infrastructure programs
to deliver which reinforces a need for external support.
Page 13 of 96
See the original
The page text is free to read. Viewing or downloading an original file needs an account.