SUPERSEDED - Approved Decision Notice - MCU25 0079 [As Published]
a. construction of a pedestrian footpath in accordance with the conditions of this Decision
Notice.
Condition 27 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Site Access and Driveways
28. A sealed access driveway must be provided from Clipper Street to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
an Operational Works approval and must include in particular:
a. a driveway crossover in accordance with Council standard drawings RS-049 and RS-
050 and any associated addendum.
Car Parking
29. A minimum of 6 car parking spaces must be provided and marked on the site. The works
must be undertaken in accordance with an Operational Works approval, be generally in
accordance with the approved plans and must include in particular:
a. 1 visitor parking spaces within the total;
b. dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities.
Pedestrian and Bicycle Facilities
30. Pedestrian and bicycle facilities must be provided for the development. The works must be
undertaken in accordance with an Operational Works approval, and must include in
particular:
a. a 1.5m metre wide footpath within the road verge for the entire length of the site’s
frontage to Clipper and Ventura Street – the footpath’s width can be reduced (to a
minimum of 1.2m), only in locations where a 1.5m wide footpath would impede on
minimum clearances (i.e., street trees) or result in the creation of trip hazards for
pedestrians;
Condition 30 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Stormwater Drainage
31. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with an Operational Works
approval, be generally in accordance with reference document Stormwater Management
Report (S22-011, Rev. C) dated 17 July 2025 prepared by Westera and must include in
particular:
a. an amended Stormwater Management Report to include 3,000 litres of rain water
storage per dwelling for non-potable reuse purposes.
b. the treatment of rainwater to achieve the load reduction targets outlined in Acceptable
Outcome 6.2 of the Water Quality and Drainage Code.
c. the attenuation of the post-development peak flow rate to be consistent with the pre-
development peak flow rate.
Condition 31 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Services
32. Underground reticulated electricity and telecommunication services must be provided to
Units 1-3 in accordance with the standards and requirements of the relevant service provider.
Page 5 of 16
Document Set ID: 24381517
Version: 4, Version Date: 17/12/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original