SUPERSEDED Negotiated Report (Representations made) OPW25 0042 (As Published) · OPW25/0042
(*) Refer to Advisory Note
Existing Condition 11g
11. An updated Construction/Traffic Management Plan and Traffic Guidance Scheme must be
submitted to Council for agreement prior to the pre-start meeting and must specifically
address the following:
g. Establishment of a communication protocol including an on onsite public information
session, and correspondence to adjoining owners, emergency services and local
businesses to advise of agreed construction times, impacts on traffic and services and
other relevant issues.
Applicant’s Request
The applicant has requested existing condition 11g be amended and replaced with the following
amended condition:
11. An updated Construction/Traffic Management Plan and Traffic Guidance Scheme must be
submitted to Council for agreement prior to the pre-start meeting and must specifically
address the following:
g. Establishment of a communication protocol in the form of an information and
response website including an on onsite public information session, and
correspondence to adjoining owners, emergency services and local businesses to
advise of agreed construction times, impacts on traffic and services and other relevant
issues.
Assessment of Request
The applicant has requested to substitute the onsite public information session with an interactive
‘one stop shop’ website for information distribution and complaint resolution. The applicant has
expressed concern that an onsite public information session is likely to attract those opposed to
the development and believes the request is unreasonable given an approval has been issued.
Engineering considers the proposal an improvement from the original condition and is supportive
of the request.
Recommendation
It is recommended existing condition 11g be amended to read as follows:
11. An updated Construction/Traffic Management Plan and Traffic Guidance Scheme must be
submitted to Council for agreement prior to the pre-start meeting and must specifically
address the following:
g. Establishment of a communication protocol in the form of an information and
response website including an on onsite public information session, and
correspondence to adjoining owners, emergency services and local businesses to
advise of agreed construction times, impacts on traffic and services and other relevant
issues.
Existing Condition 11h
11. An updated Construction/Traffic Management Plan and Traffic Guidance Scheme must be
submitted to Council for agreement prior to the pre-start meeting and must specifically
address the following:
h. Include a post out to the local residents and businesses, including all the residents
along the haulage route up to Reef-Eenie Creek roundabout advising of the proposed
development including the expected time frames and the site contact details.
Applicant’s Request
Page 4 of 7
Document Set ID: 24109099
Version: 6, Version Date: 25/09/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Negotiated Report (Representations made) OPW25 0042 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 142 KB (small file)
- File type
No other editions are linked here.