Original source · versioned page text
2016-07-18 General Committee Meeting Notes
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING 18 JULY 2016
83. Digital detailed designs including drawings, calculations, specifications and a
schedule of works, shall be submitted with any application for a Development
Permit for Operational Works in respect of roadworks and stormwater drainage
works. The design shall be in accordance with Council’s Planning Scheme
Policy PSP05 – Engineering Design Standards – Roads, Drainage and
Earthworks. To avoid conflict with underground pipes or services, all existing
and proposed services required by the development shall be shown on the
plans.
84. To facilitate production of As Constructed drawings it is suggested that all
design drawings are submitted in the Asset Design and As Constructed (ADAC)
digital format. (Guidelines on the use of ADAC are available at
www.adac.com.au).
85. A construction management plan/strategy shall be prepared by a suitably
qualified Registered Professional Engineer and submitted to Council in
conjunction with any application for Operational Works. The construction
management plan shall ensure no damage occurs to Council services and that
any adverse impact on the local area due to the construction works is within the
acceptable limit and properly managed to the satisfaction of Council.
86. A Traffic Management Plan for the each separate demolition and construction
phase of the development shall be submitted to and approved by Council at
least 5 working days prior to the commencement of any Demolition or Building
works or at least 5 working days prior to the pre-start meeting for Operational
Works. The Traffic Management Plan shall include but not be limited to:
86.1. Mitigate any adverse impact and disturbance on the local residential area
and on the traffic in the local and main roads to acceptable limits
86.2. Mitigate dust disturbance caused by vehicles and machinery movements
86.3. Limit the routes for the heavy vehicles to the major road network and limit
the use of the local roads within residential area as access to the site
86.4. Indicate provision for on-site and off-site parking for the required
workforce
86.5. Indicate the location of loading and unloading areas
86.6. Indicate the location of any “holding” areas for heavy vehicles
86.7. Operating hours.
Note - the Elm Street frontage of site shall not be used for access, parking or
loading and unloading during construction (and post construction) phase unless
a specific written permit obtained from the Department of Main Roads.
87. Any damage caused to any public utility during the course of construction shall
be repaired to Council’s standards and at no cost to Council.
88. Any alteration of any public utility or other facilities necessitated by the
development of the land or associated construction works external to the site
shall be at no cost to Council.
89. The transportation of all materials to and from the site shall be undertaken in a
manner such that no particle matter escapes onto a public road. All vehicles
carrying materials either to or from the site shall be covered to prevent
materials including dust being windblown from the vehicle.
Page 14 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.