Original source · versioned page text
2016-07-18 General Committee Meeting Notes
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING 18 JULY 2016
90. As Constructed drawings and data shall be certified by a qualified experienced
Civil Engineer for design intent, and a Licensed Surveyor shall certify the
cadastre and the location, level and type of all services and structures. All of
which shall be submitted to Council for checking and for Council’s records.
The data must fully detail levels for all engineering works including but not
limited to roadworks, pathway, sewer main, water supply main, finished ground
levels and pavement surface levels and drainage structures that will become
Council asset. The data shall be submitted in the Asset Design and As
Constructed (ADAC) digital format. (Guidelines on the use of ADAC are
available at www.adac.com.au).
Approval of works shall not be granted until all As Constructed information has
been supplied and accepted by Council.
Waste Management
91. A Waste Management Plan (construction and demolition) shall be submitted
prior to demolition, removal or relocation of any building other than a shed.
Waste Management Plan (construction and demolition) is also required for
construction of 15 or more dwelling units or for any business use of greater than
500m².
Waste Management Plans (construction and demolition) are required to be
submitted in accordance with Planning Scheme Policy 11, Waste Management
Plans see table below. Waste storage areas are to provide for adequate
separation of all reusable, recyclable and waste materials. These shall be
located so that they are convenient and safe to use. The Plan shall contain the
following information:
The site area for the storage and separation of waste is to be shown on the
plan drawings accompanying the application.
A waste management table as indicated below is to be completed showing how
waste material is to be segregated - recycled – reused or disposed.
MATERIALS ON-SITE DESTINATION
Re-use and Recycling Disposal
Expected waste Estimated On-site Off-site *specify
materials volume *specify proposed *specify contractor and
(m³) re-use or on-site contractor and landfill site or
recycling methods recycling outlet other disposal
site
Excavation material
Green waste
Bricks
Concrete
Timber-please
specify
Plasterboard
Metals - please
specify
Asbestos
Other - please
specify
Note * If a demolition contractor is undertaking works, then the Waste Management table is to
be completed by the demolition contractor.
Page 15 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.