RFI response - Land Design Rehab Management Plan Pottery St

Attached to the e-mail RFI Response, land Design Rehab Management Plan - Re: 19660 - 30 Pottery St - Request to restart the clock for decision Making period - OPW26/0033.

of 7
                                                                                                                                                          NOTES
                                                                                                                                                          •   Topsoil - is to be ameliorated site soil
                                                                                         NO CLEARING ZONES
                                                                                                                                                              or imported AS 4419 soils.

                                                                                                                                                          •   Street Tree Setout - The final street
                                                                                                                                                              tree planting locations may vary due to
                                                                                                                                                              the final driveway access points and
                                                                                                                                                              underground services.

                                                                                                                                                          •   Street Trees - Plant stock must meet
                                                                                                                                                              AS 2303:2018 Tree Stock for
                                                                                                                                                              Landscape Use. Planting to be carried
VEGETATION COVENANT AREA 7,675m2                                                                                                                              out as per Planting Schedule on LD-03.
          (Refer to LD-05)
                                                                                                                                                          •   Bioretention Basin Batters - To have
                                                                                                                                                              100mm topsoil installed over
                                                                                                                                                              cultivated subgrade. 100mm of forest
                                                                                                                                                              mulch to all areas and pinned with
                                                                                                                                                              400GSM coir netting up to height of
                                                                                                                                                              water discharge points or and/or on
                                                                                                                                                              slopes greater than 1:4. Planting to be
                                                                                                                                                              carried out as per Planting Schedule on
                                                                                                                                                              LD-03.

                                                                                                                                                          •   Bio Bioretention Basin Floor -
                                                                                                                                                              Sacrificial turf on is to be removed and
                                                                                                                                                              disposed of after 80% of residential
                                                                                                                                                              lots have built on. Filtration media to be
                                                                                                                                                              re-profiled and topped up to correct
                                                                                                                                                              levels if required.
                  NO CLEARING ZONE
                                                                                                                                                          •   Bio Bioretention Basin Floor - Is to
                                                                                                                                                              have 75mm thick layer of sugar cane
                                                                                                                                                              mulch applied, secured with 400GSM
                                                                                                BIORETENTION BASIN                                            coir netting and pinned with 300mm
                                                                                                                                                              pins. Planting to be carried out as per
                                                                                                  (Refer to LD-03 for
                                                                                                                                                              Planting Schedule on LD-03.
                                                                                                 Planting Schedule)




                                                     PROJECT     30 POTTERY ST, POMONA                                  ISSUE      DATE    DESCRIPTION

                               294 COLES CREEK RD,
                                 COORAN QLD 4569
                                                     CLIENT      BRIAN NAISMITH DEVELOPMENT CONSULTANT                   A      03/07/26   For Approval

                               PHONE: 0417 619 457
                                                                                                                                                              SHEET LD-02
                            [email protected]
                                                     DOC TITLE   LD-RMP POTTERY ST
                             WWW.FLORAFIED.COM.AU
                                                     DATE        03/07/2026                  DRAWN    JF   ISSUE   A

Log in to download the original (RFI response - Land Design Rehab Management Plan Pottery St.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.