State Planning Policy (April 2016)
Appendix 3, SPP Code: Water Quality
Performance
Acceptable Outcomes (AO) Response
Outcomes (PO)
Plan to avoid/minimise new impacts
PO1 AO1.1
The development is A site stormwater quality management plan (SQMP) is Complies. Refer to ADG
planned and designed prepared, and: Engineers Civil Engineering
considering the land a. is consistent with any local area stormwater Report for further details.
use constraints of the management planning, and
site for achieving b. provides for achievable stormwater quality treatment
stormwater design measures meeting design objectives listed below in
Table A (construction phase) and Table B (post
objectives.
construction phase), or current best practice
environmental management, reflecting land use
constraints, such as:
• erosive, dispersive and/or saline soil types
• landscape features (including landform)
• acid sulfate soil and management of nutrients of
concern
• rainfall erosivity.
PO2 AO2.1
Development does not A wastewater management plan (WWMP) is prepared by a Not applicable.
discharge wastewater suitably qualified person and addresses: Development does not
to a waterway or off site include on-site waste
a. wastewater type, and
unless demonstrated water treatment. Existing
to be best practice b. climatic conditions, and Council sewer
environmental c. water quality objectives (WQOs), and infrastructure to service
management d. best-practice environmental management, and the proposed
for that site. development.
AO2.2 A02.2 – N/A
The WWMP provides that wastewater is managed in
accordance with a waste management hierarchy that:
a. avoids wastewater discharges to waterways, or
b. if wastewater discharge to waterways cannot
practicably be avoided, minimises wastewater
discharge to waterways by re-use, recycling, recovery
and treatment for disposal to sewer, surface water and
groundwater.
PO3 AO3.1
Not applicable. No
Any non-tidal artificial If the proposed development involves a non-tidal artificial
artificial waterways
waterway is located in a waterway:
a. environmental values in downstream waterways proposed for future
way that is compatible
are protected, and development.
with the land use
constraints of the site for b. any groundwater recharge areas are not affected,
protecting water and
environmental values in c. the location of the waterway incorporates low lying
areas of a catchment connected to an existing
existing natural
waterway, and
waterways.
d. existing areas of ponded water are included, and
Project Address – Project Description
ADG Engineers Aust. Pty Ltd
Page 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.